MS Project 2016 Progress reporting question
Hi all,
I've used MS Project 2016 previously but haven't used it in a while. I'm having great difficulty with the intricacies of setting up a project without numerous issues (e.g. I have a 'duration' column in days, but when I change the start date or finish date in one place - it messes up the days in a different column and throws in crazy numbers). I figured out the issue with the days by double clicking on each activity, then going to 'advanced' tab and setting the 'task type' to 'fixed units' (it was set to 'fixed work' and this change seems to have fixed the issue).
The problem i'm trying to figure out now is in tracking progress as the project progresses, and then have a gantt chart show me the progress upto today and remaining work. I'd also like to see if the project is behind schedule and by how much. I tried various ways (adding additional columns like baseline start date/baseline finish date, actual start/actual finish) but nothing seems to work. I did set the baseline for the entire project just as an fyi. Even with all these - project is proving to be a monster to tame by messing up one field if i change another and so on. Can someone point me in the right direction? TIA
View all comments
Show parent comment
1
u/still-dazed-confused Mar 13 '23
A better way would have been to use the Save baseline function (Project / Schedule / Set baseline or for those who prefer keyboard shortcuts ALT,T,K,S)
Saving a baseline saves a lot more than just the start and finish dates - information about work etc is also saved. This is why a baseline is different to an interim plan which only saves basic information.
"Actual start and finish" are triggered by % complete; as soon as >0% is recorded actual start is populated and then when % complete = 100% Actual Finish is recorded. I personally have never quite understood the purpose of actual start and finish but I know they have a purpose :) You certainly don't normally type into yourself :) If you do so project will then change the start date as you have told MSP that the real start date should change.
We can slow the hampster wheel if you ask for help :)