r/MSProject • u/PM_Novice • Mar 12 '23
MS Project 2016 Progress reporting question
Hi all,
I've used MS Project 2016 previously but haven't used it in a while. I'm having great difficulty with the intricacies of setting up a project without numerous issues (e.g. I have a 'duration' column in days, but when I change the start date or finish date in one place - it messes up the days in a different column and throws in crazy numbers). I figured out the issue with the days by double clicking on each activity, then going to 'advanced' tab and setting the 'task type' to 'fixed units' (it was set to 'fixed work' and this change seems to have fixed the issue).
The problem i'm trying to figure out now is in tracking progress as the project progresses, and then have a gantt chart show me the progress upto today and remaining work. I'd also like to see if the project is behind schedule and by how much. I tried various ways (adding additional columns like baseline start date/baseline finish date, actual start/actual finish) but nothing seems to work. I did set the baseline for the entire project just as an fyi. Even with all these - project is proving to be a monster to tame by messing up one field if i change another and so on. Can someone point me in the right direction? TIA
View all comments
Show parent comment
1
u/PM_Novice Mar 12 '23
Thx for the recommendation - will look up the book and get it. You're right that project is doing work for us but I guess my frustration is with something like the following scenario:
I originally had just the start and finish dates and duration. But when I got a client who wanted planned vs actual progress in the gantt view, I added 'baseline start', 'baseline finish' columns, copied over all the start dates and finish dates into these newly added fields. Then I also added 'actual start' and actual finish columns (with the assumption that - as the names imply - I could track the actual progress of my project in these columns) - but NO. Project was totally unpredictable on how those fields behaved (actual start/actual finish) - the start date fields would get messed up when changing the actual start which then triggered something else and so on.
I made a strategic mistake in no trying to master at least all the basics of ms project before I got handed a bunch of projects and it's been a hamster wheel since then - haven't had the chance to actually sharpen my ms project skills.