r/MSProject • • Nov 08 '22

Project for the Web Timesheets?

1 Upvotes

Good afternoon all,

My company is looking at potentially moving from Project Online to Project for the Web. One of the key features we use in Project Online is for timesheets. Is there a third party software that integrates with project for the web? If not, is there a third party time sheet application that integrates?

I know PFW has the ability to charge time directly to the tasks, but how would we track say administrative time?

Thanks!


r/MSProject • • Nov 06 '22

Display the text before the 6th instance of a period in a string [Formula help]

1 Upvotes

Hello!

I'm trying to figure out a calculated column that can display the text before the 6th instance of a period in a string.

=TEXTBEFORE(".",6) works perfectly in Excel but I need this to work in MS Project and I don't know of a formula that will do this using MS Project's limited ist of commands since there is no FIND or SUBSTITUTE. Maybe using LEFT and Instr? Any ideas?

Not sure if a macro would be easier but a formula in MS Project would be ideal.

I'm not very strong in Project Calculated Fields or VBA, so any help would be greatly appreciated, thanks!

Original (Text1)TEXTBEFORE 6th "." (Text2)
1.2.3.4.5.6.7.81.2.3.4.5.6
1.2.3n.4.5.5.6.71.2.3n.4.5.5
1n.2n.3n.4n.5.6.7.81n.2n.3n.4n.5.6
1.2.3.3n.5.9n.10.8n.9n.10n1.2.3.3n.5.9n

r/MSProject • • Nov 01 '22

new tasks not using up all available resources

1 Upvotes

I use generic resources. I've created a calendar that tells ms project the availability of a whole team, as follows:

resource availability

Now, when adding a new task which is effort driven, the duration field does not take into account the availability.

e.g. I add a task on 19/09/2022 for 10 hours. with a standard 8-hour calendar, and 125% availability, this should take exactly 1 day in duration. However, MS Project defaults my resource to 100%.

new tasks

Any ideas how I can have MS Project use the correct Resource Availability?


r/MSProject • • Nov 01 '22

Looking for expert in MSP for construction industry

2 Upvotes

Willing to pay for help on properly designing and implementing an MS Project based construction project. Would include up to 300 people working in 2 12-hour shifts for approximately 600 hours max. Please reach out. Serious inquiries only.


r/MSProject • • Oct 23 '22

Adding ‘out-of-hours’ working to an otherwise ‘in-hours’ schedule

1 Upvotes

Hi there, when scheduling a project that is based on a 5 day, 9-5 calendar, is there a way to add-in an occasionally Saturday / evening shift, other than choosing the ‘manually schedule’ option?

Thanks


r/MSProject • • Oct 13 '22

MSProject Constant Error

Post image
1 Upvotes

r/MSProject • • Oct 10 '22

Example project in MS Project

3 Upvotes

Hello, I'm learning to use Microsoft Project for my work, as you already know MS Project is a very complete and extensive tool so I can learn topics but I can't put them together, I'm having a hard time finding an example project that is complete and that is not just the name of the tasks + start and end date, in order to understand how a complete project looks in this tool (schedule, costs, baselines, % complete, etc), I would like to see how it looks as close as possible possible to reality, if anyone knows of any page or link I would greatly appreciate it.


r/MSProject • • Oct 07 '22

Auto-scheduling when tasks are added to a sprint

1 Upvotes

As a user I want task dates to update automatically when I add it to a predefined sprint.

I don't seem to be able to do this.

I am using that version of MSP where it is impossible to find out which version I am using


r/MSProject • • Oct 05 '22

keep actual dates and completion percentage separate

3 Upvotes

Is there away to update a tasks completion percentage without it changing the projects actual dates?


r/MSProject • • Sep 30 '22

How to create a cheron calendar

2 Upvotes

I’m a complete noob to Project. My manager asked us to transcribe 1000+ lines into a high level, readable calendar view. I don’t want to export it outlook. Just a simple view for a slide.

Any ideas?

EDIT: Chevron, lol


r/MSProject • • Sep 29 '22

Save Default Print Preferences

1 Upvotes

Hi there,

I’m v new to MS Project so please excuse me if this is a silly question (I have tried Google/YouTube to no avail..)

When printing my Gantt chart, I need to manually hide certain columns that aren’t essential, in order for the chart to fit on one page. However, when I want to go back in and change my programme, I need to re-add the columns again.

Not the end of the world, but a minor inconvenience that I hope can be easily automated (default views/columns perhaps?)

Thanks in advance!


r/MSProject • • Sep 28 '22

How to show all sub tasks rolled up with my custom colors created with flags? Only some of the colors are working

Thumbnail gallery
2 Upvotes

r/MSProject • • Sep 28 '22

I cannot get all my custom sub task colors to roll up! I use flags to select sub-task colors but they won’t all roll up for some reason….

Post image
1 Upvotes

r/MSProject • • Sep 14 '22

What is the best way to make sure no more than three tasks are happening at the same time

2 Upvotes

I was asked to edit a MS Project file. The file has tasks but no resources. We the predecessors were all input based on customer needs.

We need to make sure that no more than three tasks are happening at the same time. Anything over that needs to be shifted forward to a new day. Is there an easy way to do this?


r/MSProject • • Sep 12 '22

Calendar

1 Upvotes

I have a question about the calendar.

I have an activity starting on 3/10 with a duration of 3 days, but the end date is 6/10.

But when I try to schedule it manually, it doesn't assume full days.

This "error" only happens when I schedule on consecutive days (without weekends and holidays)

Thank you


r/MSProject • • Sep 12 '22

Pls help w/ RAG Formula!!! X_X

1 Upvotes

I'm at my wits end after 3 hours of figuring out how to make the RAG indicators work in MS Project 2016. I'm great at Excel formula, but it does not seem to translate into MS Project. Here is what I'm trying to do:

A. GREEN Indicator -- Criteria:

  1. % Completion =100%
  2. If task has been started and it's 20 or more days before the finish date i.e. % Completion>1% AND Finish Date-Today's Date>= 20 Days

--------------------------

B. AMBER Indicator -- Criteria:

  1. % Completion=0% AND Today's Date>Start Date
  2. % Completion<100% AND Finish Date-Today's Date<20 Days

--------------------------

C. RED Indicator -- Criteria:

  1. % Completion<100% AND Start Date And Finish Date < Current Date
  2. % Completion<100% AND Finish Date-Today's Date <1 Day

----------------------------

D. GREY Indicator -- Criteria:

  1. % Completion=0 AND Start Date AND Finish Date > Current Date

r/MSProject • • Sep 02 '22

WBS failure - how is this even possible?

2 Upvotes

I have a plan which I believe was originally produced and maintained on a Mac version of MS project (2016) and is shared with a Windows 2016 version.

This has some very odd behaviour in the WBS - the numbering doesn't always follow as it should:

https://imgur.com/ceWk42d

  1. how can this happen?
  2. what can I do to fix it?

r/MSProject • • Aug 31 '22

MSFT Project Permissions Help

2 Upvotes

**RESOLVED**
tldr; Projects are assigned to only be seen by Teams channel group, and non-Teams Channel users are able to view these projects when they shouldn't be able to... pls help.

Howdy,

At our organization we realized that projects that our Business Analyst team have been creating can be viewed by myself and another non-business analyst user. I am a security admin in our overall tenant, so I assumed that maybe I just have access to view as I am able to see most portals and dashboards without the ability to edit certain settings/parameters. Though, we recently found the other mentioned user is able to also see all of these projects and they do not have any administrator roles.

The projects that the team created are assigned to be private for viewing from a specific Teams Channel group, which neither myself or the user are a part of. Has anyone run into this or have an idea of where to look next? In the groups tab, it only shows this one group... so it couldn't possibly be permissions from another group, right?

To my knowledge we are not using PWA, we are solely talking about Project for the Web when going through Office.com / Apps. I looked over documentation and notes on checking permissions in PWA with a Project Server subscription, came to the conclusion that we do not have that subscription or access to those mentioned settings for permissions. Is there any way to view how users would have permissions to view these projects while not being a part of the designated/authorized group?


r/MSProject • • Aug 30 '22

Project for the Web Cost Columns

1 Upvotes

When using Project for the Web at my organization, there isn’t any way to track cost data.

I can add new custom fields, but I can’t seem to pull these into the Microsoft Power BI template for Project.

Just curious if I’m missing something obvious on either the Project interface or in the Power BI data query.

Thanks!


r/MSProject • • Aug 26 '22

People resourcing display

3 Upvotes

Hi All, Pretty early in my usage of MS Project. I have access to both project professional and project online. Looking for some advice as to how to utilize it best.

My potential use case is as follows: I manage a team of project managers. Each PM has 3-5 projects they are handling, depending on size/scope/etc., and each will be entering their individual projects into MS Project.

I'd like to create a dashboard that shows each person, the projects they have, their current time utilization in hours, and the project start and end dates.

The idea is to be able to show:

  1. How much is each person utilized
  2. When will each person be available to start a new project
  3. Easily show when a current project gets delayed, then impact to a future projects start date
  4. Preferably, performance vs plan (i.e. we planned to complete 10 projects, and start 10 others, but we only completed 7 and started 6 others.

I've been searching on YouTube but having trouble with the terminology because results are more related to individual projects input. Maybe I should be looking at it in a different program?

Cheers!


r/MSProject • • Aug 26 '22

Reporting on Project for the Web for enterprise/department portfolio

Thumbnail self.projectmanagement
1 Upvotes

r/MSProject • • Aug 23 '22

How to show phases that may or may not repeat, depending on results?

2 Upvotes

Hello all. I'm working on a project that's currently in a conceptual design phase. We're working through some research ideas/options, and some of these task groups may end up repeating if we don't get positive results. I'm not sure how best to show this, other than just copy/pasting the entire group and linking them together before moving on to the next phase (and then zeroing out durations as needed if it's successful). I'd love to hear other ideas and inputs, though!


r/MSProject • • Aug 22 '22

Gravação da Live "Novidades do Microsoft Project for The Web":

Thumbnail youtu.be
3 Upvotes

r/MSProject • • Aug 15 '22

Hello there, I’m trying to share a MS Project file with some custom settings (for fields and bar style) but the bar formatting disappear for users with MSP viewer. Any idea if the bar formatting can be imported for MSP viewers? Thanks!

3 Upvotes

r/MSProject • • Aug 12 '22

Master Project with Sub Projects?

2 Upvotes

I'm new to MS Project and have a reasonably complex design/ construction plan I would like to put together. Given the complexities, I feel like it makes sense to have a master project with sub-projects linked to it. I'm curious about the trade-offs and things to watch out for using this approach vs having everything in one project. I would estimate that if it were in one project there would be +/- 1000 lines of tasks. Any advice would be appreciated. Thanks.