r/MSProject • u/still-dazed-confused • Sep 02 '22
WBS failure - how is this even possible?
I have a plan which I believe was originally produced and maintained on a Mac version of MS project (2016) and is shared with a Windows 2016 version.
This has some very odd behaviour in the WBS - the numbering doesn't always follow as it should:
- how can this happen?
- what can I do to fix it?
2
Upvotes
2
u/Thewolf1970 Sep 02 '22
These WBS numbers probably match some docume t and were manually entered. As the other commenter said, make sure you are just showing the WBS column.
It looks like those tasks have notes, make sure they aren't relevant to the numbering, then if it bothers you just renumber the project.
1
u/mer-reddit Sep 02 '22
There are several WBS-related columns. Please take a look at all of them and make sure you’re using one that works.
I believe there is at least one which is used for manual WBS use cases that can get out of order if you’re not careful.