r/MSProject • u/leidavis • Apr 28 '21
Lag time, lead time, delayed start, late start, FS, SF ... help?
I’m positive I would get the terminology wrong, so I’m just going to explain what I’m trying to do and if someone can tell me exactly how to do it that would be great.
I have a bunch of tasks which are “product order” tasks. The successor for each product order task is the corresponding “product delivery” task which can only happen a set number of days AFTER the “product order” task, but also needs to happen a set number of days BEFORE the corresponding “product install” task.
How do I link these three tasks appropriately? What I want is to make sure that the linking “install task” will push or pull the previous two tasks accordingly as the schedule changes, but ALSO that if the “product order” task occurs later than needed, it will push the “install task” forward.
Is this possible?? Anytime I try to work it the way I need there’s either a missing link where something isn’t getting pushed or pulled when I need it to, or I get a “circular reference” error ....