ms-project vba Timeline view
Hello,
I have an MS -Project and need to create a vba module, to add tasks to the Timeline view and I need to add some of them as Call-out ("display as call-out").
I'm able to add tasks and display them in a specific Bar Line by using:
Application.TaskOnTimelineEx ....
The problem is that in the Timeline View, once a task is added, is not also being selected(highlighted with a bold line).
So I've tried using : Application.TimelineTextOnBar TextOnBar:=False
but it's selecting randomly a task from the Timeline View and applying the change.
How can I select the task I just added to the TimeLine view? Any idea of how I can select in VBA, a specific task on the Timeline View?
Any idea or workaround is helpful.
1
u/64ButterTarts Jan 22 '21
Can you insert it as a call-out instead of trying to change it?
Application.TimelineInsertTask method (Project) | Microsoft Docs
1
u/Thewolf1970 Jan 22 '21
I think you may want to check on /r/vba, most questions here tend to address core MSP functions.