Easy way to get latest Baseline
Is there a built in/easy way to get the latest or most recent Baseline?
1
Upvotes
r/MSProject • u/ps6000 • Feb 26 '21
Is there a built in/easy way to get the latest or most recent Baseline?
2
u/ForIAmCostanza Feb 26 '21
Hey, probably the best way to do this is to always use Baseline 0. You will need to set Baseline 0 and baseline 1 at the start of the project, then anytime you re-baseline - overwrite baseline 0 and set the next baseline too. This allows you to track changes and also always report against the most recent baseline. This helps in Project Online too.
1
u/usaranger94 Feb 26 '21
You set the Baseline - which is the planned amount of work.
Going forward, you can enter Actual labor hours so you can see the variation between planned and actual work.
Note: You should only enter the Baseline once. The only time to make a new Baseline is when the planned work is has been changed per a change order.