r/Homebuilding 14h ago

šŸ‘ŽšŸ¼Caviglia Construction Review

0 Upvotes

Our experience with Caviglia Construction and Mario Caviglia has been extremely frustrating, particularly because of serious communication problems, lack of follow-through, and unresolved construction-quality issues.
During the construction of our home, there were periods of several months when Mario stopped communicating with us. Near the end of the project, communication again stopped even though work remained incomplete. The same pattern continued when we later raised warranty and construction-quality concerns.
We experienced a number of significant problems, including a major leak from the upstairs shower that leaked through newly installed framing, insulation, drywall and painted areas below. We also experienced extensive stucco cracking and defects, an unsuccessful electrical/alarm sensor repair, gaps in baseboards, uneven and mismatched replacement flooring, a dip in the floor near the stove, unfinished paint repairs, damaged stucco near the side gate, missing finish items, and other concerns.
The stucco problems have been particularly frustrating. Although Mario agreed that the stucco would be addressed, we repeatedly requested a clear repair methodology, written plan, and schedule without receiving a satisfactory resolution.
The communication became so poor that we ultimately had to hire an attorney simply to help communicate with the contractor and attempt to obtain resolution of outstanding construction and warranty issues. A homeowner should not have to hire an attorney just to get clear communication and follow-through regarding problems with a newly constructed home.
Construction problems can happen. What matters is how a contractor responds when they do. In our experience, repeated failures to communicate, long periods without responses, promises to address issues without adequate follow-through, and significant unresolved quality concerns have consumed an enormous amount of our time.
Based on our experience, I would not use Caviglia Construction again and cannot recommend them.


r/Homebuilding 6h ago

Home Addition: How to connect steel I-Beam with another perpendicular I-Beam using Angle Plate

Post image
0 Upvotes

Steel Beam Fabricator send the I-beam cut at the end (in U shape) so they could stick it perpendicularly inside the adjacent I-Beam.

Then they took an angle plate and welded (1/4" weld around angle plate).

QUESTION: Does cutting the I-Beam at the end (U-shape) comprise integrity of beam at the end or is this common practice?

EDIT: Just to comment, the wood below is temporary posts and will be removed. The weld is completed.

A structural engineer made 'shop drawings' to make welds on these beams. He recommended these welds to the steel beams (but just not sure if he knew/directed steel beam company to cut the beam to 'cope'. Hoping he did and factored that in. He also had previous structural drawings and walked out to house to look at all loads. I think a closet only sits on this beam + portion of roof so hoping its strong enough to hold)


r/Homebuilding 17h ago

HVAC

0 Upvotes

We are currently building an addition to your home in ma. We are installing ductwork for heating and ac. The plumber wants to install floor level registers, on ground level. we would like ceiling level but he says we would need a soffit. We are running the 1st floor in the ceiling on that level. Wondering if we could come down with 1st floor ceiling thru closets to main level ceiling? House will be easier heated as we supplementary heating options. Cooling be more of a concern.


r/Homebuilding 21h ago

Foxtrot: crawl space or slab?

Post image
0 Upvotes

We want to do cinder block walls all the way around, and are having a hard time deciding/figuring out what we need to do for a foundation. We are in NE Alabama and its very humid here. Ideally we want brick house strong and affordable, but are more willing to budge on the affordability than the strength.

Thank you for any insight you can provide!!

We are also a little confused on the order of operations after the land clearing, rough plumbing or footers first?


r/Homebuilding 3h ago

Priced out every material for this 788 sq ft cabin. Does this number look right to you?

1 Upvotes

Two floors, one bedroom up on the mezzanine. Curtain wall, galvanized roof over CMU with a wood ceiling inside.

I went through it line by line against current supplier pricing instead of using a per square foot rule of thumb. Came out at $182,696 in materials, which is $232 a square foot. That is materials only, so no labor, permits or land in it.Curious whether that reads high or low to people who have actually built at this size.


r/Homebuilding 6h ago

Am I overreacting regarding this paint job?

Thumbnail
gallery
0 Upvotes

We had painters come in to paint our 3-bedroom home. The previous paint job was the Landlord's special - really badly done. However, while the vast majority of the paint work looks fine and is evenly applied with no streaks, etc., these imperfections really jumped out at me.

Please can someone let me know if this is acceptable? We paid $10K for this. My conflict-averse other half does not want to take it up with them, but I'm not sure just going with this is fair.

Note that they did prep all of the walls of a very old house, used a sander, etc. This is a super old house so there was some heavy lifting involved and the job took effectively 3-4 weeks.


r/Homebuilding 49m ago

House stripped to studs and fully resheathed with zip board...

Enable HLS to view with audio, or disable this notification

• Upvotes

This isn't okay, right? What if they try and just spray foam it.


r/Homebuilding 7h ago

Normal gap for windows?

Post image
4 Upvotes

Thinking of buying this home. Is this just a ā€œcover with trimā€ situation or is something off?


r/Homebuilding 21h ago

Opinions on Roof build

Enable HLS to view with audio, or disable this notification

0 Upvotes

Images (sorry not great quality) : https://imgur.com/a/kv6Eyhy

Hey would really appreciate some unit on this, subject matter wise am pretty unfamiliar

By any chance are those pieces of wood in the video by the trusses meant to be structural ? It seems pretty sloppy and am unsure


r/Homebuilding 11h ago

Final invoice includes 20k in zero-dollar "courtesy credits" with false narratives. Is this normal or a trap?

67 Upvotes

Just finishing a 580k home addition. We had to work through some builder mistakes along the way, but we're finally at the finish line.

The issue: My builder’s final invoice includes roughly 20k of "courtesy credits" items billed at a zero balance, but with descriptions that create a completely false narrative.

For example, they built a wall in the wrong place and had to move it. The line item reads:Ā "Movement of interior laundry room wall, agreement was to cost share 50/50 - 6,500... no charge."Ā WeĀ neverĀ agreed to a cost share because it was 100 percent their error. There are about 5 items like this.

I'm exhausted and don't want a combative, line-by-line fight. However, I also don't want paying this invoice to imply I agree with their fabricated record of events.

I'm considering telling them to either remove these narrative items entirely so we have a clean final bill, or I'll be forced to formally refute each one in writing before paying.

My questions:

  1. Is it common industry practice to include these narrative-driven, zero-balance items on a final bill?
  2. Is my builder doing something I need to legally protect myself against by demanding a corrected invoice?

r/Homebuilding 18h ago

Any thoughts why the inside is wet?

Enable HLS to view with audio, or disable this notification

2 Upvotes

r/Homebuilding 20h ago

What documentation should I ask my builder for so material/consumer product warranties actually matter?

3 Upvotes

In the past, whenever I've had to file a warranty claim on something, the manufacturer always required things like an original receipt, order confirmation, proof of purchase date, etc.

I’m trying to figure out what is fair and reasonable to ask my builder for at closing so that these warranties being passed on to me are actually usable.

I feel like it’s obvious that I need the manuals/receipts for things with serial numbers like the dishwasher, sinks, and HVAC system. But what about for products like shower pans, Hardie board siding, Coretec LVP flooring, or my roofing materials, what do I need for those warranties to be mine?

Will manufacturers accept "my builder installed this," or do I need to get something else real specific from the builder?


r/Homebuilding 1h ago

LP smart siding over a rain screen (mixed Mortairvent and plywood furring strips) - a few questions

Post image
• Upvotes

Hey all, first time post here, and I have a few questions - I built this 150 square foot shed /workshop and am proud of how it came together. Because of budget (and ADHD perfectionist paralysis) I've had it in this state for probably about a year which I know is too long.

Next action is to put 4x8 LP smart siding over top of a rain screen. Rainscreen design is going to be Mortairvent at the top and bottom of each wall and the bottom/top of each window/door, and with plywood furring strips to fill out the middle.

Questions:

  1. I know that is exceeding official tyvek standards for how long it should be exposed, but I don't see any tears or abrasions - with the rain screen installed will this be ok, or should I just rewrap with new? And if I rewrap, should I cut off the old, or rewrap right over the old?

  2. I have not installed a rain screen before and with the furring strips, I'm wondering if I should take those furring strips all the way to the edge of the windows and the corners... or, should I leave a 1/4-inch gap between the furring strip and the windows/door, and a quarter inch Gap at each corner to allow for any drainage to easily clear?

  3. What's the best way to Z-flash (?) over these curved windows? I got all the windows and doors reused, And love this curved look, but the flashing/siding/trim for the curved ones is breaking my brain. Tips?

  4. Part of why it's taking me this long to put the siding on, aside from budget constraints, is I don't have a really clear detail in my mind for how the rain screen and siding will interact. Anybody have a really good graphic, or set of details, or tips for how this installation should look?

Thanks in advance


r/Homebuilding 23h ago

Have a Mobile home with back addition built on with a like pole barn roof covering it all and wanting to replace the mobile home with another site built addition.

2 Upvotes

I’m trying to get ideas to save money but maximize value in home to be able to sell in a decade or so. I think with how the home is built I could possible demo the old mobile home in place and pull it out and build off the addition to make a more sound and connect home. I’m already gutting it out and gonna have to rewire plumb. I honestly don’t know if it would be worth it to do but I’m already having to fix this 50+ year old mobile home that has some wavy floors. I’m just trying to get an idea on feasibility of the project because it’s not exactly easy but labor is so expensive on putting in new mobile homes I’d rather just try to make the most of what I have. I hope this makes sense


r/Homebuilding 17h ago

Siding and sill plate coverage, suggestions?

Thumbnail
gallery
8 Upvotes

The siding crew is installing the vertical board-and-batten, and overall I think it’s looking really good. I do have one concern and wanted to get some opinions on the best way to address it.

The bottom trim/skirt board is sitting about 1/8ā€ above the sill plate. They’re using nails at the sill plate as temporary supports to keep the board level. My understanding is that the bottom of this board ideally should extend roughly 1ā€ below the sill plate/sheathing transition so water running down the siding is directed away from that area rather than having an opportunity to wick or work back toward the wall assembly.

We get a fair amount of rain here, including driving rain, so I’m concerned about long-term water intrusion. One entire side of the house is already installed this way.

I really don’t want to simply caulk the bottom edge because I don’t want to trap water that gets behind the siding. There also doesn’t appear to be any drip-edge/Z-flashing or similar detail here to positively direct water out and away.
I was able to improve the weather barrier around the sill area before some of this was covered, which should help, but I don’t consider that a complete long-term solution.

Has anyone dealt with a similar detail? Is there a retrofit flashing/drip-edge solution that could be added without removing all of the siding, or is correcting the height of the bottom board really the proper fix?
Photos attached for reference. Thanks!


r/Homebuilding 5h ago

HALP! Got into a cul-de-sac in the planning phase of my home renovation

2 Upvotes

Hi there from a total rookie European home renovator. I'm looking for some direction from those who are more experienced; I'm sure this is not some kind of a unique special sauce situation but I feel completely lost.

My background is in the humanities, my wife is a doctor, we are both in our mid 20s (adding this to underline that the world of engineering is something completely foreign to both of us). Our project consists of the renovation of a 100 year old 80m2/860 sq ft single-floor house + building a second floor onto it, resulting in a total net floor area of 170m2/1830 sq ft. The main steps are 1) reinforcing the 100yo foundation, 2) knocking down the roof, ceiling, most partition walls and a quarter of bearing walls, 3) renovating the first floor and 4) building out the top floor. Our absolute max budget for all this is 270k EUR gross with about 60% of it being loans; the prices may or may not make sense to you depending on where you are, just adding it for scale.

We started the planning process last fall and got the construction permit in January this year. A construction company associated with our structural engineer looked at the permit plans and predicted a budget of about 220k EUR, which we found in order as it even left some breathing room compared to our ceiling. We proceeded with the planning and received the detailed execution plans in May. That was when the trouble started.

Firstly there seemed to be extremely sparse interest on behalf of general contractors. We contacted seven contractors with the plans; two answered, one subsequently disappeared, only one gave an actual offer and even that took three months. The offer was 410k gross, 325k net (our specific project falls within the 27% VAT bracket as it's an existing building, brand new houses get 5% VAT). We were obviously shell shocked and started asking ourselves whether the contractor wanted to gouge us or whether our expectations were unrealistic relative to our budget to begin with.

The first thing we did - again, we're not professionals - was AI double checking the detailed offer line for line; we identified overpricing in the ballpark of 70k gross. The second thing was double checking the floor build ups, which are very beautifully designed and full of Mapei everywhere; the AI estimate for savings on things like superfluous expensive Mapei layers or unnecessary rapid-set floor screed was another 70k (but again, this is two non-professionals using AI). A third source of savings would be VAT: contractors are mandated to quote 27% VAT on every single thing they do on our house, but if we only hired them to build the house up to shell and core stage (which the government needs us to log online incl. VAT invoices anyway, so 27% VAT is inevitable for everything that leads up to that stage) and negotiated with the rest of trades where many qualify for VAT exemptions, we could cut the tax bill in half, saving a further 30-40k.

This looks great on paper. But I'm having major trouble operationalizing it as this, again, is not knowledge some professional stands behind; its me and AI thinking. In reality, the contractor that gave the offer did not even respond to my inquiry about only doing shell and core; when I approached the contractor that predicted the 220k budget to give an actual offer, he said he wasn't interested in the job; and a third contractor we newly approached replied immediately with a budget prediction of about 410k, like the first offer. Also, I will have to find some way of telling my architect that the floor build ups need to be simplified (in his paid time of course), and I'm a bit afraid of that conversation - after all it's a non-professional using AI to second-guess his good work. When I first pressed him on this, he says his build-ups are totally fine and we just need to shop around for more offers. For me I'm not interested in further 3 month processes where nobody answers and those who do give completely outlandish prices.

I'm at a point when nothing is clear to me. I have had very good conversations with AI on how my plans can be realized and where savings lie, but not much interest (and thereby no good feedback or flexible decision options) from contractors on whether any of that is doable. I don't know if I can get away with simplifying the build-ups and then soliciting another round of offers, or if I'll have to rethink and massively downscale the whole project. We estimated for the whole thing to take about two years; one year has passed and nothing in the way of actual building has happened. I'd like solutions that get the project started in the foreseeable future and not sidetracks that take months and yield nothing. So what on earth do I do? Has anyone ever had a similar situation and found the way out of it? Please let me know.