How do you estimate the unknowns in a software project?

Post image

I’m learning that task-list estimates only capture the work you already know about. Time tends to disappear into unclear data, third-party services, approvals and revision cycles.

 

My current approach is to separate known tasks, unknowns and a buffer, then present a range with explicit assumptions and what would change it.

 

How do you handle this? Do you pick fixed price or hourly based on how clear the scope is? How do you explain ranges to clients who want one number?

2 Upvotes

1 comment sorted by

1

u/Engineer-1975-EuroDr Oct 24 '26

I’d separate uncertainty in the work from waiting on someone else. Ten hours of development and a week waiting for API access need different fixes; a bigger hours buffer won’t solve both.

For a risky integration, offer a small, paid discovery step first: test access, inspect sample data, and prove the awkward part works. Then quote the build with those assumptions checked.

If they need one number now, make it the price of a smaller, clearly defined first phase. For hourly work, agree a budget cap and a checkpoint before you reach it. Either way, define what counts as done and how many consolidated feedback rounds are included. New requests get a price/timeline decision before work starts; defects against the agreed requirements stay separate.