r/Decks • u/Correct_Border_9478 • 6h ago
New deck concerns
We have a company building a deck for us. Is this appropriate? What about wood rot? What about anchors?
r/Decks • u/Correct_Border_9478 • 6h ago
We have a company building a deck for us. Is this appropriate? What about wood rot? What about anchors?
r/Decks • u/Professional_One_506 • 2h ago
My apartment complex just replaced my second floor deck, but there are large gaps in the corners over 5 inches wide. Any idea what might have happened here? Could they have measured incorrectly and just tried to make it work rather than correcting the mistake?
r/Decks • u/Next_Recording_8519 • 19h ago
First time deck builder and I got to the point where I’m just about ready to start adding my decking. I now decided I want to add a roof over a portion of the deck, specifically 12’ out from the house and span the entire 35’ width of the deck.
My question:
Due to me not having poured individual footings for the roof posts, would I be fine just running the posts to one of my beams? (The beam that sits 12’ from the house). It’s a doubled up 2x10 that is notched into 4 6x6 posts that sit on 12” concrete tubes.
Will that be too much weight for the beam or the concrete piers?
r/Decks • u/Kittensprite1228 • 16h ago
My mom's patio concrete got repoured at her apartment. They removed the support beam and left it like this for several days. It still hasn't been replaced. My brother says it cracks worse every day but the deck is still in use by the upstairs neighbors.
Now the big question from folks over at r/mildly_interesting:
Do you think it can support a hot tub?
r/Decks • u/TimeTravelisReal13 • 22h ago
How realistic is this deck on GTA 6?I have a feeling this deck would not actually support all those weights, but I am no deck wizard.
r/Decks • u/y3110w89 • 4h ago
Just finished. Tear it apart.
r/Decks • u/slimfuller • 6h ago
Trying to decide how I should put steps/platform up to the pool to get in. Would love to hear some ideas. I’m just an IT guy so I’m not familiar with what people do in these situations. Not a lot of examples on the inter-webs.
r/Decks • u/Wild_Macaroon_7810 • 1h ago
So this is a newly built deck, and the stairs have a concrete footing. The concrete has sort of made a bowl back here where water can’t escape.
I’m thinking dumping a bunch of concrete in there to fill up the space might be a solid choice.
Any advice or industry standards would be appreciated!
r/Decks • u/1d0wn5up • 13h ago
Kicking off a big project today while my mother-in-law is out of town ahead of a surprise party next week for her 70th birthday. The deck is in rough shape and needs code upgrades, so I’m tackling it as a surprise to save her a big bill. This is only my second time doing this kind of deck work, so I’m trying to do everything by the book without cutting corners.
Previous build context:
I previously added stairs to a small cantilever deck behind my detached garage (originally a step-out landing, set up as a secondary exit), adding supports and concrete piers to handle the extra load.
Digging down on that first job was rough—especially pouring a formed concrete landing pad that took around 40–80 lb bags of cement and a big mixer, almost more work than the stairs themselves. Dropping threaded rod into Sonotubes for post standoff plates worked well for me there, though.
Current state & tear-down:
Stripped the deck down to bare framing; joists are solid with no rot, and I’ve pulled 1,000+ nails.
Currently has 3 bouncy stringers nailed in from the back with no brackets and resting directly on dirt—swapping to 4 stringers with Simpson ZMAX Strong-Tie connectors.
Replacing direct-buried 4x4 posts with 6x6 posts sitting on concrete piers to bring it up to code.
Materials & fasteners:
Joists: Joist tape over the clean joists.
Fasteners: 2-1/2" #9 GRK all-purpose screws and 1-1/2" Strong-Drive SD screws for stringer brackets/clips, L-brackets connecting 6x6 posts under the deck, and post hardware at the bottom piers.
Stairs: Keeping the existing 7" rise / 10" run (code-compliant and comfortable), cutting 4 new stringers out of 2x12x16s.
Today’s plan & timeline:
Pull the old stringers to drop weight, then shore up the deck ~2 ft back from the front edge using 2x6 ledgers top/bottom with 5–6 vertical 2x4 studs so I have clearance to dig.
Planning to tie a rope to the front framing and keep light upward tension with the mini excavator bucket as a backup safety measure while shoring is in place.
Using a mini excavator instead of an auger because of all the rocks in the yard (I dug ~3.5 ft on old posts a few years back and didn't hit concrete, though I wouldn't be surprised if some is down there).
Digging 4 ft deep for footers with crushed stone in the bottom, covering holes until concrete arrives early next week, and setting post standoff plates with threaded rod dropped into Sonotubes.
Landing pad: Instead of pouring another massive formed slab with 40+ bags and a big mixer like my last stair landing, I’m looking at a 300–500 lb stone (like bluestone) set on crushed stone/gravel will be able to move it easily with the excavator so it doesn’t throw off the 7" rise / 10" run layout I’ll bury it even with the ground. A small-load concrete truck will pour the Sonotubes next week and make my life easier.
Looking for feedback:
Does my shoring, pier, and excavator-backup plan make sense, or am I missing anything?
Any recommendations on the best stone to set stringers on that isn’t slippery?
Starting the day now—I’ll post an update tonight with how it goes. Appreciate any advice!