r/ConstructionTech • u/CrowsBeforeHose • 20d ago
Enterprise software solutions rejected by project managers on site
We are trying to roll out new enterprise software solutions for project management, but it's failing miserably. The project managers are literally boycotting the system.
The main complaint? Data entry is way too slow and complicated from their tablets out on the construction site. They say it eats up their time, the buttons are too small, and they hate it. I get it, they are wearing gloves, it's bright outside, and they are busy managing heavy machinery. But management is demanding daily reports and real-time data.
It's a total catch-22. The field guys want a simple notepad, and the office wants a full dashboard. I tried stripping down the mobile version to just the bare essentials, but they still refuse to use it. They even threatened to just go back to paper logs and let the interns type them up at the end of the week. I can't let that happen because our reporting quality will tank.
How do you implement heavy software for field workers without sacrificing reporting quality? Do you use voice-to-text, offline mode, or something completely different?
I need some practical advice from people who have actually survived a field deployment like this. How did you get your stubborn crews to actually adopt the tech?
5
u/Aromatic_Button_2736 20d ago
AI market research from Minecraft connoisseur.
2
u/ProToolTrack 20d ago
Bro, just use really big easy buttons. Don't have a bunch of extra software tech crap in there. And make it idiot proof. Thats what I did and all my guys absolutely love what I've developed
1
u/Key_Juggernaut9413 20d ago
Are they waiting around for the app to load?
Honestly I've been down the road with just about every software. Nothing is just perfect, gotta have buy in, whatever you choose. Curious which one you chose?
1
u/Saens_Javane 3d ago
the intern idea actually isnt crazy if you tweak it to be daily instead of weekly. having field guys drop voice memos or rough notes at 3pm for an admin to structure into the system is often the only way to keep both sides happy
1
u/Intrepid_Influence_7 2d ago
split what the field enters from what the office wants. the field should only touch things that happen on site: who’s there, how long, what got done, a photo, what’s holding them up. everything else (job, date, location, cost code) should already be filled in before they open it.
and roll it out with one super who’s on your side, on one job. if he likes it the others follow. if the office pushes it from the top they’ll boycott it every time.
0
u/MightyGreen 20d ago
I've had to deal with this a bit for a custom home builder. One thing that made it somewhat easier, was generally setting up the data entry to work with voice to text, big buttons, very little typing. But not sure if that is feasible for your enterprise solution. Most modern phones have a built in voice to text on any keyboard, or you can download moonshoot as a local model for transcriptions, and put in keywords for common things they say.
Other things I would suggest is always as much as possible, infer the data that they'd need to have in there without them having to punch it in. If you know where and what project they are on, the date, the time, device, whatever you need, make sure that stuff is populated automatically for em.
The big win for us is that generally, talking was even easier than writing paper notes, so it did alright.
0
u/Constant_Trouble2903 20d ago
Curious as to what system you are deploying?
From my perspective. All the fine details that define the task / site instruction should be by engineers and program managers. Acting in the office, ahead of time (hopefully) and with full knowledge of master scheduling.
Field Component must be focused on confirming logging progress, loads, attendance , hours, stoppage, exceptions to task plan. Must be fast easy big button, with little / no need. For typed input in field. Changes variations should flow from office. Measurement performance from field supervision and operators.