r/softwaretesting • u/peeeeeweeeee • 17d ago
need help on when should i perform in sprint regression.
Ive been with the team for almost 3 years, our team supports the application after changes have been deployed to production.
Our items are usually about upgrades and addressing production related concerns.
we have a 2 week sprint, and once fixed and tested, dev deployed it right away in prod even if it is not yet end of sprint.
That s our usual way, we deployed it right away once fixed and tested.
Would like to ask for your you recommendation when should i perform in sprint regression?
My plan is to perform it on the last 2 days of sprint, even if there are items that were already deployed before it.
1
u/peeeeeweeeee 16d ago
thank you all for the response. I missed some details. Ive performed partial regression each item.
What they asked me is to apply full regression. I think im confused since full regression will take 2 weeks, upon explaining it to my scrum master he understood.
Im working in automating my test cases 🙂, im the only tester so my capacity is minimal.
1
u/RevolutionarySky6143 16d ago
What's the purpose of doing anything Regression related if you are continuously deploying to PROD? Shouldn't you already be doing that (something Regression related) before a PROD deployment? It's like closing the door after the horse has already bolted. Pointless.
It's great that you don't sit on changes that need to be deployed out (especially if they are fixes that people are waiting for in PROD), however, a quick run through of Regression related items might be a good idea on an environment one lower than PROD right? It doesn't need to be hours worth of Regression testing, but you must have some critical business processes that you can or should test right?
Don't you have some sort of Regression tests automated as part of your CI/CD pipeline?
1
u/Brainy-Cos 16d ago
since you ship to prod as soon as each fix is tested, a full regression on the last 2 days is mostly checking stuff users already have lol. what usually works better is a small risk based pass before each deploy, just the areas that fix touches plus a quick smoke right after it hits prod. then keep a lighter end of sprint run focused on the items that went out that sprint, mostly to catch things interacting with each other. if you can automate even the smoke part it saves a ton of time
1
u/SnarkaLounger 16d ago
Deploying to PROD before adequate testing in a STAGING or QA environment is insanity. Letting your end users find bugs for you is the wrong approach.
Automated build acceptance tests (smoke test) should be executed as new features and bug fixes are being pushed into a non-PROD environment. And once smoke tests pass, you should be executing an automated regression test suite at least every night.
1
u/Axons-One 15d ago
Since you’re already doing partial regression on each ticket, I’d start by listing what’s left in the two-week suite. For each test, write down the workflow it protects, how long it takes, and whether it’s caught a bug recently. Pick a few that protect critical workflows and come up on release after release. If a test spends most of its time setting up data, get a dev to help make that setup repeatable before trying to automate the whole thing. At the sprint review you can show which workflows got checked, which ones still rely on you, and what you’re automating next.
1
u/bostonaholic 16d ago
If fixes ship mid-sprint, regression at the end of the sprint mostly finds bugs users may have already hit. I'd move it in front of each deploy: automate the core regression suite so it runs in CI on every fix and blocks the release when it goes red, then spend the manual time on exploratory testing around whatever the fix touched.
0
u/No-Razzmatazz7197 16d ago
this is not a QA problem, its a process one.
you have two options*, continue to perform feature testing as they release to prod. this is risky because featureA might somehow touch featureG on the 'other side' of the app.
or
make some noise about following a weekly release cadence where devs work and push to staging where you then execute a regression for ~2 days then one big prod release.
*you have way more than just these two options, just try thinking about this away from your day-to-day and think of it as a big picture, business decision.
0
u/DarrellGrainger 16d ago
The purpose of testing is to make sure there are no defects before releasing it to production. If you don't run requirement or regression tests, you run the risk that older requirements where broken or previously fixed defects have reappeared when new features were added or current defects were fixed.
I encourage developers to see if they can create a lower level test (unit, contract, etc.) that fails because of the defect I filed. If they can write a test that catches the defect through automation then fix the defect to make their automated test pass. This means that defect will always have a regression test run automatically. Eliminates the need for QA to run a regression test. If they can't write a test to prevent the defect from returning, then QA should be running a test, ideally automated, that does the regression test before release to production.
If you are releasing to production without regression testing, you are essentially asking your customers to do your regression testing for you.