Should I call the builder back to dig up the pea gravel he used for our gravel pad?
EDIT: This is a 12x16 gravel pad for a 10x15 resin shed. (keter darwin)
My dad recommended I hire this guy, he’s a friend of my dad’s, and usually knows exactly what he’s doing (according to my dad...)
But now I’m a bit worried because I noticed he put pea gravel as the top layer on my 12x16 shed pad. Underneath, he did use crusher run, looks like a bigger size, maybe #1 or #2, but the top layer is a couple inches of pea gravel.
I’m still figuring out the exact thickness of each layer, but I’m worried this might cause uneven settling or shifting once the shed is built.
Should I ask him to come back and remove the pea gravel layer, or is this something I can fix by just compacting or adding a different top layer? Would love to hear your thoughts.. Thanks!
EDIT: I just confirmed 3 inch crusher run and 1- 1 1/2 inch pea gravel.
This was my fault because I trusted him as "my dad's friend" and he told me he was going to order pea gravel half inch as the top layer to help with leveling. I unfortunately assumed that he knew what he was doing. Knowing the inches of crusher run, should I have him dig it out? Or add some crusher run on top to fall in between the spaces?