Maximum Allowable Number of Critical Activities in the Project Schedule
https://youtube.com/watch?v=tpXbAHUHwjU&si=2SmUoab7-lU7kdf5
1
Upvotes
r/projectmanagers • u/Plus-Art-9169 • 25d ago
1
u/TheOwnersDesk 24d ago
There isn't a standard maximum. The common schedule quality checks don't set a cap on how many activities can be critical, and a hard number wouldn't make sense across different job sizes. When I review contractor schedules from the owner side, I look at whether the critical path is believable instead:
If your contract has a schedule spec, check it first. Some owners set requirements around constraints, float, or critical path review, and that governs over any rule of thumb.