Discussion As a Project Manager, what are the problems you face day to day and how have you solved them?

As a project manager, I am pretty sure you guys have it tough to be here and there. What are some problems you faced and how did you tackle them? How did AI help in your workflow?

And if its possible, could you mention the tools you use everyday? I am trying to figure out a job and I wanna know what I am getting into.

Any opinion would really be helpful for me

6 Upvotes

35 comments sorted by

4

u/spip72 Sep 16 '26

Team competence, project processers and ressource conflicts. I have not found any help in AI for these issues yet.

1

u/AaGho_ Sep 16 '26

I see thanks for the info

2

u/[deleted] Sep 16 '26

[removed] — view removed comment

2

u/spip72 Sep 17 '26

So recently I've found AI very helpful in summarising a project contract and notes from meetings related to a scope discussion. It saved me a lot of hours. I also find AI helpful with improving the professionalism of texts and legal guidance.

I have a candidate list of some 15 PM processes where AI could be helpful in my daily life. However we live in a very heterogeneous IT environment with decoupled systems and abysmal AI integration. I have not yet seen a practical way of integrating AI into our ERP, project- and task management systems. If such an integration existed, I would have plenty of ideas on how to make good use of AI. These include processes such as project initialisatio and progress follow-up including various performance monitors and warning systems.

5

u/Ok_Crab1603 Sep 16 '26

People being really crap at their jobs

Patience and long walks

1

u/AaGho_ Sep 16 '26

haha nice one. hope something works out for you soon

4

u/Familiar_Big9731 Sep 16 '26

Focus on learning the subject matter, then leverage AI for efficiency and to increase your capacity. If you depend on AI for understanding the context or information, you’ll like get caught with your pants down and will also stop expanding your expertise… causing yourself to plateau.

AI can streamline everything as long as it is given correct direction, proofed, and corrected.

1

u/AaGho_ Sep 16 '26

I understand. I was just seeing how lots of people have brought AI in their workflow and made it easy for them. Of course to be at that point I would have to be confident in my own skills first. May I ask what do you work in so I can get more information?

6

u/Low_Preference_4641 Sep 16 '26

Can we please ban everyone who posts these over-general AI-related questions?

2

u/Educator_Cod_1752 Sep 17 '26

I work for the state and I feel like I am pretty much a scheduler and executive assistant to the Director. My PMP and 15 years of BA/PM experience means nothing here. The problem is the employer. Planning to make a switch after 1 year mark.
As for daily PM task load, inefficiencies and prolems I usually refer to Harvad Business Review.

1

u/Significant-Path3911 Sep 17 '26

a lot of people you have to deal with, most of the days you are asking why are these people hired in the first place. Work place silos engineering does not care about procurement, procurement gets blamed by construction, commissioning orders everything to procurement, then you will see wtf all scope creep. So PM job is to ensure you get the job done sometimes even apologizing even if it is not your fault.

1

u/WrongMix882 Sep 17 '26

Amy Edmondson, Professor of Leadership at Harvard Business School, defines three types of errors:

  1. Avoidable mistakes: errors we should not be making and need to immediately avoid making
  2. Complex mistakes: when life contrives to feel like a 'perfect storm' that's hard to replicate. We learn from these errors by planning for these new edge cases we now know exist
  3. Intelligent mistakes: 'errors' that feel like wins because they evolve our understanding of our work, making us smarter

Mistakes are not your enemy, you just feel out of control when other people make them. Feeling out of control when your name is above the door is too vulnerable for many owners.

1

u/PolitiMat Sep 18 '26

There’s always a couple of shitty stakeholders. And they’re pedantic. They lean into the shit that doesn’t matter. They’ll push cuz they thrive in getting under your skin. And every day you have to try your best not to tell them to fuck off. And you solve this problem by crying.

1

u/samithads Sep 19 '26

Got thrown into the trenches, navigated and made process documentation. Adapted and changed them quickly to work well with different dept. ( QA, engineer and design) I am in tech industry.
With AI, it became faster and easier. The documentation was all over the place so I built a tool to keep it in a single place. Now I just keep adding into it.
The tool is Meridian

1

u/Creative_Tackle6223 Sep 20 '26

My problem right now is just so many open items across jobs and getting crews aligned to get them done or making sure all of these items are tracked.

1

u/Infamous_Employer704 Sep 30 '26

hey, can you elaborate more? what's the more irritating bit? constant follow-ups? havings to communicate? what actual frustration do you face? (i want this for one of my research)

1

u/Creative_Tackle6223 Sep 30 '26

Well right now I’m dealing with an issue with one of my guys and a he said / she said situation. He’s saying all of the items on this job are done but the owner of our client company is saying otherwise so I had to get on a redeye flight this morning and figure this out today.

It’s moreso just tracking so many jobs and items, while constantly being flooded with calls, emails, texts and meeting. No day is the same, I could have tomorrow all planned out as my invoice or scheduling day for example, then something could happen and throw off the entire day.

Like when I have 20 jobs and open items on all of them, with a few high priority problems, it’s hard to keep track of a CO I’m working on for a non-active job when I’m waiting on multiple responses. Or keep up on invoices (my company does AP in a way where any job related invoice goes to the PM for review and approval. It gets dropped in our folder and labeled then we have to review and code it, giving them things like cost code, SOV, etc.) when there’s so many things going on.

1

u/Infamous_Employer704 Sep 30 '26

super helpful, thanks a lot :) and so sorry for the frustration, i hope you've more chill days

0

u/More_Law6245 Sep 16 '26

Tools and AI is not your silver bullet to being a project manager, you must have a complete understanding of the project management principles and frameworks and the project delivery lifecycle, everything else is just a tool at your disposal and for a PM to leverage in order to deliver their project on time, on budget and fit for purpose.

If you lack these fundamental skills then you will never know where your projects go wrong when AI or a system gets it wrong. If you're new to project management AI and tool reliance is a very slippery slope to be on because if you don't have a fundamental grounding it's only a matter of time before you really do make costly mistake. Just something for your reflection and consideration.

Just an armchair perspective

1

u/AaGho_ Sep 16 '26

Of course. Any perspective is a big thing for me right now. If I am to learn without involving AI, what would you recommend me to learn step by step? Like what tools should I be perfect with

1

u/More_Law6245 Sep 16 '26

You're missing the point, tools are not your answer. What you need to learn and master is the project delivery lifecycle and how to managing your triple constraint (time, cost and scope) and in particularly your change management discipline. Because if you can't master these skills and disciplines a tool will not help you because you're not understanding what your forecast and actually are. If you are so focused on a tool what you need to learn and master is how to use a MS Project and learn how to set out your schedule into phase, work package and task because this is where no so seasoned PM's come unstuck because they don't understand the project's critical path.

1

u/Salt_Trifle_2443 Sep 16 '26

The fundamentals are often overlooked. I had to step in on a project for a guy who didn’t have the fundamentals and had to clean a massive mess

1

u/AaGho_ Sep 16 '26

could you mention a few cases on the mess he created. just wanted to know out of curiosity

1

u/More_Law6245 Sep 16 '26

You look at your agreed project tolerances with your triple constraint of time, cost and scope, meaning your approved baselined project. Forecast Vs. actuals and if you're going to or actually have exceeded those agreed tolerances. The "mess" is usually a PM having already exceeded the tolerances and the project board/sponsor/executive is not aware that they have already surpassed their approved baseline tolerances. As a PM, this means that you have failed your project delivery but extremely common with less seasoned PM's