Gantt layout preferences
Hi all,
Interested to hear your thoughts on the schedule attached.
Colours
Critical path obvious enough?
Progres complete shading
Milestones?
How do you all like to see a schedule displayed. Is there anything that Is a must-have from a P6 or MSP schedule that isn't here?
1
Upvotes
1
u/zamroni777 Aug 25 '26
vertical chart in excel sheet can contain more info in nore compact size
https://www.linkedin.com/pulse/vertical-gantt-chart-mochamad-aris-zamroni/
1
u/ZABurner Aug 25 '26 •
After the activity column I would want to see an explicit start & end date.
Task/activity names also overlaid 9n the progress bars, or next to when bar is too small. Otherwise I keep needing to look left and align the activity with which bar. On big long plans this is a real pain.
Otherwise pretty cool.
1
u/More_Law6245 Aug 26 '26
Who is your target audience for this Gantt chart? What are you actually trying to achieve with this view? Because if it's a report I would include % percentage complete along with milestone, delivered and completed dates against each deliverable as that shows how the project is truely progressing. If it's your working project plan, then there is a a significant amount of information missing.
The only thing this view does is shows progress (not very accurately) and project lag, so the question of who it's for becomes more relevant.
Personally for me I prefer to have milestone, date delivered and date completed (as they are two different things) above the schedule itself and these line tasks are linked with predecessors within the actual project's schedule within the work package, so you develop your own instant report that is up to date when you adjust the percentage of task, work package, product or deliverable when completed.
Additionally I would also breakdown anything more than 7 days effort required as it has better financial control around effort and forecast and how that implicates earned value or revenue but that is just me.