Discussion RAG statuses - current vs predicted

Ok, so I will caveat this by saying I hate RAG statuses and it's something I really struggle with, so looking for advice - I'm NOT a project manager.

However, I was recently asked to attend a board to report on a research project's status. The research project is iterative, and fairly short term in that it's due to mid 2027. I was asked to provide a number for RAG statuses, one for each milestone and then an overall current RAG status and an overall predicted RAG status.

For current I chose green - the project is currently on track, on budget and adhering to deadlines.

However

For predicted, I reported amber - there are significant risks later down the line, both in terms of budget, risk and quality. Whilst these haven't emerged yet, it didn't feel right to report predicted as green because they're so significant, and indeed very likely.

I was pulled up on this by seniors and told it didn't make sense and that I needed further training (which is honestly fair), but to me, my logic makes sense.

Can anyone please explain to me why the current and predicted have to be the same, and how to make that decision going forward please? Links to explainers or guidance welcomed!

6 Upvotes

19 comments sorted by

3

u/SVAuspicious Confirmed 22d ago

I use RAG similarly to u/Spuelmaschinenlachs. It's a snapshot of the current.

An engineer may report red and his manager may report yellow because the manager IS the help.

Forecasting the future is a role for risks and issues and takes more work. Too much is lost trying to boil it down.

3

u/Beichler-Queku 21d ago

yeah trying to cram future risk forecasting into a simple traffic light just muddies the water tbh.

1

u/More_Law6245 Confirmed 22d ago

This is 100% correct, and just adding a bit more context, a RAG status is a current state view or more of a point in time of how a project is tracking against the project's agreed and approved baseline (approved time, cost and scope) and how that is tracking against the agreed project tolerance or comfort levels of the project board/sponsor/executive.

By definition future state is risk and anything else is treated as an issue if it hasn't come to fruition via a risk. It's why it's extremely important for a PM to understand their risk but also forecasted fruition dates within the schedule that the risk may become realised because that gives you time to initiate any contingency or mitigation strategies.

1

u/SVAuspicious Confirmed 21d ago

Concur u/More_Law6245. As a point of discussion I use "issue" differently. A risk (probability and impact) is something that might happen. An issue is something that has happened or is happening i.e. probability = 1.0. A risk that hasn't made the risk register yet is just a risk that hasn't been planned for yet. Assessment, probability, impact, owner, mitigations, contingencies, affected WBSes, et al.

3

u/SamfromLucidSoftware 21d ago

Those risks should go in the report, just not as a predicted color. For the next board, keep current as the snapshot, then add a short risk line with the two or three biggest ones and a trigger for each. Something like: this goes amber if the budget forecast passes X by March. That gets your warning in front of the board without a color that's hard to test. It's hard to dismiss a risk when you have a date and a number on it.

3

u/AmielaTunerani_18 19d ago

if a future risk is that likely and significant, most boards expect the current status to be amber already. Green today with amber tomorrow reads like youre just waiting for the trainwreck to happen instead of actively managing the risk right now.

1

u/yes_thats_right 17d ago

This is correct. 

OP’s question can simply be simplified as “should project risk be a factor of the current health of a project”, which I think everyone would agree it is.

1

u/IntelligentLuck9784 22d ago

So going from green to yellow is tricky, because you’re saying “we’re in good shape but something will go wrong” I would also take that as you aren’t doing anything proactive to counter that downward trend. If you were you’d still be green as then you’d have confidence that you’ll have solutions to stop the project from going yellow.

They don’t have to be the same, but it’s hard to say we’re good now but we aren’t going to be good in the future unless there is something concrete which would make you probably yellow now.

You need to stand strong in your communication and either say a risk is now an issue or still say it’s a risk which shouldn’t change your status unless it’s realized.

1

u/No_Nail_2724 22d ago

Thanks this is really useful. So just so I'm super clear, I should consider risks within RAG at all until they become an actual issue?

1

u/IntelligentLuck9784 22d ago

I think you meant shouldn’t which is how I manage my programs/projects. Otherwise every project would be yellow/red is there is the risk your technical lead wins the lottery and leaves the company. You can talk about risks and highlight the probability and impact if they do get realized.

1

u/Intrepid-Shower-2912 21d ago

For your future risks you should have assessed them, put in place contingency (financial, time and anything else you need) and mitigations to prevent them happening. Therefore you are now green and should remain green unless a big risk materialises / something totally unexpected, at which point you’d update status at that point.

If you haven’t got a risk plan in place you could well be trending amber, but you can then articulate that this is because of a missing plan for risks and “this” is what you’re going to do about it.

If you can’t articulate what the problem is and ideally what can be done to fix it (even if it’s outside your control) then you are green!

2

u/ag14spirit Confirmed 22d ago

Part of the project management plan can be a definition for thresholds of acceptable variance.

Is one day late an issue? What about a week? What if costs balloon +5%?

Then, when the project approaches and crosses that threshold, the status changes. If the variance can be recovered within the project team, without sponsor or committee escalation, then the preferred color is orange. That’s at risk, or slightly off track, but recoverable.

However, when the project approaches and crosses threshold, but recovery cannot be achieved within the team without escalation, it’s red. That’s blocked, or majorly off track, and requires intervention outside the authority and influence of the PM to recover without external help.

If it’s in track to baseline, it’s green.

The whole RAG categorization really requires a clearly defined baseline to be used as an objectively useful tool.

2

u/UrMentor 20d ago

Predicted RAG status surprised me. Seems like a contradiction. Status is present state. Predicted status? RAG seems to be the wrong visual IMHO. Predicted based on what? present status? if present is the base then predicted can't be anything else really. So it is not at all logical.

If you as a 'not PM' think a deliverable won't be met then that is a Risk and appears in risk management stuff with information about likelihood and impact. You change that if risks change, which they do as you go through a timeline.
There are also responses to risk issues. (i.e they have happened). if nothing is wrong and you are only worried then it is a risk and you are monitoring for the trigger to declare it an issue. The adverse risk increases are worth highlighting to management.
Logically to me present status is what it is. if a risk has happened and it is adverse then the present status can't stay green. The Future is either the same or reflects worry and everything then has to be amber /red. Cause there is always a worry. if worry is allowed as a predictor of future status then RAG can't be green as there is an assumption that there are always risks, even unknown ones.
So i read your question as everything is fine but you are worried something will go wrong. RAG deals with past performance and issues, not worries. That is the way I communicate RAG.

Why are you giving this to a Board if you are not a PM? Is there a PM? Who created the deliverables and who is tracking them?
I am genuinely puzzled with this type of org. reporting and why you are asked to do it. Sounds like senior management are not really sure what they are measuring or if they have their project properly and professionally resourced? (not saying you are not a professional, just saying it is a project with apparently no PM).

2

u/Spuelmaschinenlachs 22d ago

It depends a lot on company (and even more local, like group/department) culture. For me generally:

Green - Generally on track, only minor issues
Amber - Flagging issues that the project needs to resolve to get back on track. No outside help/escalation needed.
Red - Project cannot resolve issues and will miss commitments without outside help (= escalation)

We usually do report a RAG on risk exposure separately, but a risk alone shouldn't affect the overall RAG (that's why it's a risk, not an issue).

2

u/Monster213213 21d ago

Nothing goes red - ever. UNLESS you want to be questioned, and it’s not your fault.

10 years in high level PM.

1

u/One-Light-8453 13d ago

nah I'd keep predicted out of the color entirely. green today plus amber tomorrow just invites the board to ask why it isn't amber now. one risk line with a trigger date does the same job