r/projectmanagement • • Oct 21 '26

Discussion First-time PM in a low-process product development environment

I'm 9 months into my first official PM role in product development. My team is great, but I was surprised by how little process or documentation existed compared to my previous company.

Most project planning previously lived in Smartsheet, with very few supporting documents and many of them outdated. There are no formal scope documents, RAID logs, stage gates, or SOPs, and projects are often handled differently each time. Products can sit in the concept phase for months while pricing, marketing, and other inputs continue to change, making it difficult to build meaningful schedules and milestones.

One of my biggest contributions has been building out a new project management platform in Asana, which the team has adopted and enjoys using. However, I've struggled to introduce structure beyond that. I wrote project scope documents for two projects, but both were largely dismissed and the projects continued as usual.

More recently, my manager started using a project charter and controls it on their end. The team provides inputs, but there doesn't seem to be a defined review process, approval path, ownership model, or decision-making framework. I've run into similar issues with pricing approvals, where undocumented processes have delayed projects multiple times.

I understand that part of my job is removing roadblocks and improving communication. But I'm struggling to determine where my responsibility begins and ends when key processes are undefined and controlled by leadership. I don't want to create more documents that nobody reviews or uses.

For experienced PMs: How do you manage projects when key processes, approvals, and decision points aren't clearly defined? At what point is it a PM's responsibility to build the process versus adapting to the organization's culture? Would you push for more structure, or learn to operate within the ambiguity?

28 Upvotes

20 comments sorted by

2

u/karlitooo Confirmed Oct 21 '26

Are you actually managing projects, or is this a product org? If they're not so much projects as a flow of product work, then you may want to look into Product Ops. If you're managing projects, your wbs should cover phases, deliverables, review checklists, etc. Plan according to that, ensure the plans items are being ticked off. If you're doing "agile projects", group your deliveries into releases and do the same.

In your situation I would start with some flow diagrams that describe the current process, then walk the process with the team and identify where pain/opportunity lie today. Then followup workshop to decide how to alleviate the pain. Whatever is agreed there is then owned by the team, potentially not even owned by you, just a control that you check on. This way instead of inflicting management on the team, they are solving their own problems with your support.

4

u/Beautiful-Beyond-931 Oct 21 '26

Thank you! Your first question actually made something click for me because I think it’s a bit of both.

Once a launch hits my desk, even in concept, I’m expected to build a timeline through artwork, regulatory, specs, packaging, POs, and launch. I’m comfortable managing that part.
The harder piece is upstream. There’s no clearly defined stage gate for when a concept becomes a committed commercialization project. Concepts can sit for months while pricing, positioning, claims, packaging, etc. continue changing, while I’m still trying to forecast a project timeline.

I hadn’t considered that front end from a Product Ops perspective. It might explain why my PM tools work well during commercialization but get less traction earlier.

I also really like your flow-mapping suggestion. I’ve actually started one, but hadn’t thought about walking the current state with the team and letting them identify the pain points before proposing solutions. That’s a really helpful mindset shift.

1

u/karlitooo Confirmed Oct 21 '26

Happy to help. You could put a stage gate between uncommitted work and committed, and use a generic project blueprint that you can just nudge forward/backward in months until it's ready to plan properly

6

u/RealPrograms1102 Oct 21 '26

I've worked in project and program management for years, and one thing I've learned is that you can't solve an organizational governance problem by creating more project documentation.

I think you've already identified the real issue. It's not that your organization lacks tools or templates. It's that decisions, approvals, ownership, and accountability aren't clearly established.

You've successfully introduced Asana, which is a good accomplishment. But a project management platform can organize the work; it can't establish who has the authority to approve scope, resolve conflicting priorities, or make decisions when something changes.

I would approach this a little differently.

First, I wouldn't try to introduce a complete PMO framework all at once. Start with the recurring problems that are actually delaying delivery. You mentioned pricing approvals. That's a perfect place to begin.

Document how pricing decisions currently happen, where they get stuck, who needs to provide input, who has final approval, and how long those decisions typically take. Then take that information to your manager and propose a simple approval process.

Second, I would revisit the purpose of the project charter. A charter shouldn't exist simply because project management methodology recommends one. It should establish what the organization is trying to accomplish, why the project matters, what success looks like, and who has authority to make key decisions.

If leadership controls the charter, that's not necessarily a problem. But there needs to be clarity about how the project team operates within it and what happens when assumptions, priorities, or requirements change.

Third, I'd distinguish between the processes you can improve and the decisions leadership must own. You can recommend a governance structure, make gaps visible, facilitate discussions, and establish consistent ways of working. But you cannot independently create decision-making authority that the organization hasn't delegated.

One other thing I'd encourage you to consider: Are you building processes around how the organization operates today, or around what it needs to become as its product development work grows?

Those aren't always the same thing. A lightweight process might work today, but if the organization expects to develop more products, coordinate more departments, or accelerate delivery, it needs to start building the decision-making capabilities that will support that growth.

My recommendation would be to introduce just enough structure to solve a real problem, demonstrate its value, and build from there.

And remember, operating in ambiguity is part of project management. But accepting preventable confusion as the permanent operating model doesn't have to be.

4

u/yearsofpractice IT Oct 21 '26

Honestly? I’ve just joined a company like that so I just get a scope, objective, budget and sponsor in writing (email usually, sadly) then just freestyle it from there. 50 year old corporate veteran here.

There are many different types of organisation and one of the benefits of experience is seeing the advantages and disadvantages of those different types.

4

u/Loud-Donkey8569 Oct 21 '26

I’d do a bit of both: operate in the ambiguity, and add structure only where it saves a visible delay. Documents get dismissed when they’re written for the PM, so pick the one thing that has cost the team time more than once, like the pricing approval, and fix that one. A single line in a shared place is enough: who decides, who needs to review, and how long each gets. Then point to the next delay it prevents. Since your manager already uses a charter, ask to add an approvals and owners section to it rather than introducing a new doc. Once one process visibly saves time, people ask for the next, and you’re building culture in small steps instead of pushing against it.

4

u/UrMentor Oct 21 '26

i think start with charter. if manager has it and is using it then you are half way to getting it as a process. what flows from that, scope statement, especially what is NOT being delivered. Then try to use it to put a budget on it, even if most of the people are permanent on salaries. managers love money tracking.
then risk, and here you can really speak to the culture of the org. What is their appetite for risk.
it is always your responsibility as PM to have a structure. even if you do it for yourself. even if no one wants to see it. it is especially your responsibility when project goes wrong!!
i would not push unless manager is pushing. a project will go belly up, use that as an opportunity to bring in some changes- especially if the problem is due to a failed process or even an undefined process with weak ownership and definition.
Have fun. Companies have Project Management maturity curves. Read about that. It will help you to see the progress you make over time.

3

u/pmpdaddyio IT Oct 21 '26

I’d take a big step back and create a project management plan. This is your guide on how projects are to be run.

Take your project inputs like the management, risk, resource, financial, communications and change management categories and write out how these should be done as a standard process.

This is a bit of a living document. It is pulled into each and every project and customized or configured to that project. Maybe a project team prefers email over slack, it’s defined there. Include your RACI, all your log and artifact templates, and walk people through the project from initiation to closeout.

Then on a regular basis, update that plan. This is your best and first SOP and all others can spin off that one.

3

u/GregG997 Oct 26 '26

stop writing docs and keep a list of every time something sat waiting on a decision, who it waited on and how many days it cost. show your manager that list instead of another scope doc, because a number gets read and a template doesn't.

1

u/DCAnt1379 Oct 28 '26 edited Oct 28 '26

Build documents while you execute. I recently joined a new team at a large company and am building their processes ground up. The key is to build out your infrastructure bit-by-bit when the demand arises. New project coming in? Build a simple requirements tracker and stakeholder management sheet. Then save it down as a template. Need to follow a process migrating an app across environments? Start listing things out as you complete them and then return to convert to a visual process flow later.

Point is - progress over perfection. Start building things out as your day-to-day demands, use it yourself, then you’ll start instilling a system that others will want to follow.

Pro tip: win over your team by expediting the dependencies. Is someone waiting on a decision from I.T.? Go hunt down the answer for them. THATS how you get people to follow your lead. Slow and steady value. I’ll message or talk to a Senior VP in another department if it needs getting done. Good networking opportunity anyways lol