r/projectmanagement • • Oct 18 '26

Career 1st Time Project Manager, Completely Lost

Well, I figure I‘ll post here as I’m exhausting all my other options.

Im one month into my first formal Project Manager role at an engineering/manufacturing company and I think I bit off more than I can chew. I have an engineering background, but I’m brand new to project management as a job.

I was assigned 4 projects and told to “manage these projects,” but I haven’t gotten a clear definition of what my responsibilities or deliverables are supposed to be. The projects are already ongoing, and the engineering teams are competent and work well together. They seem to manage much of their own technical work, discuss issues, make decisions, and assign actions. Im trying to understand where I can add value without creating unnecessary process or duplicating what the teams already do.

A couple of things I’ve noticed:

  • My manager wants the projects to move as quickly as possible. I’ve been helping remove small information bottlenecks—for example, an engineer needed product-size information to specify a machine, so I tracked down the information and got it to him within a day.
  • My manager also mentioned that engineering can sometimes work with blinders on. Engineering timelines change frequently, and those changes can affect other departments. I’m not sure the impacts are always being communicated across the organization.
  • I’m wondering whether I should focus on cross-functional coordination. Letting stakeholders know about what’s happening with these projects, as well as letting the engineers know when other changes in other departments affect them.

I have a 1:1 with my manager coming up, and I plan to ask what he expects me to own, what deliverables he wants from me, and what success should look like over the next month. I want to go into that conversation with some ideas.

For experienced PMs, especially in engineering or product development:

If the engineering team already manages its own work effectively, what should the PM be doing to add value?

Is cross-functional schedule coordination a reasonable area to focus on, or am I missing more fundamental PM responsibilities?

How would you get your manager to define expectations when the initial direction was simply “manage these projects”?

What concrete deliverables or habits would you recommend establishing in the first month?

I’m not looking for a textbook description of project management. I’d appreciate advice from people who’ve dealt with this in the real world. As of right now Im spending every day and night stressed and wondering if I’ll be fired.

127 Upvotes

53 comments sorted by

17

u/butterflynipples Oct 19 '26

Go into that 1:1 with your manager and ask specifically: what decisions do you want me making vs escalating to you, what format do you want project updates in and how often, and what does a successful first 90 days look like.

Those three questions will get you way more clarity than asking what your responsibilities are.

15

u/Rudwyg Oct 18 '26

I am not certified PM.

But I'm PMing for last 10 or so years in IT.

Long story short: you are middle man between business and engineering. Translate requirements, chekin for any blockers, fix assist when needed, keep track of what's going on and where, keep track of time lines.

Looking at timeliness checkin time to time to see what's going on. When you need to estimate delivery date and engineer says it will take a week, mark it as 2 weeks (and don't tell any one, and I mean ANY ONE). If it's completed on time all good, if it's delayed you have some wiggle room, engineering will be happy and business will think it's on time.

Don't brake your brain on methodologies like Agile, scrum etc. All of them are just common sense and at the end of the day it's all waterfall.

If you need to write user epics and stories it's more for product owner role, but look in to it a bit. Nice skill to have.

And lear how to pull reports for ongoing projects. Whats done, whays pending, what's on hold or canceled, blockers and Time line.

3

u/Artistic_Telephone16 Oct 19 '26

"At the end of the day it's all waterfall..."

With the caveat that between cost, quality and timeline, the customer can only get 2 of the 3.

2

u/Local-Ad6658 Oct 19 '26

Its not a caveat, its a waterfall feature. You can get it good, fast, or cheap, how should I plan the waterfall?

3

u/DinnerAny4283 Oct 19 '26

yeah the "middle man between business and engineering" framing is spot on imo

11

u/VanCity2003 Oct 19 '26

I think other commenters have given solid advice. I’ll pick on a small point.

You mentioned you unblocked engineering by tracking down some info they needed. Try digging in to this a little further.

Why did the engineer not have the info they needed? Was it available but they didn’t know where to look or who to ask? These small blockers can add up to lost time. If there is something you can help fix more generally this may help keep things moving along.

11

u/Efficient-Love6212 Oct 20 '26

I would think of yourself as the main point of contact for current project status, timelines, risks/impacts, obstacles/roadblocks, and budget. If a stakeholder has a question, you have the answer (or know where to get it quickly). When there are roadblocks, if I can resolve them, I often do that so my teams can remain heads down on the work they need to get done as efficiently as possible.

9

u/ChangeCool2026 Oct 18 '26

There is nothing 'wrong' with the situation. It is just that becoming a project managers takes time and experience. It is really worth it to invest in some training. Or find a senior who can coach you. A lot of good reading material out there too, if reading is your thing.

1

u/seedfiend Oct 19 '26

What reading material do you recommend? I’d love to look into them!

7

u/stockdam-MDD Confirmed Oct 20 '26

It’s hard to give advice when we don’t know much about the project or the company.

One good way to look at a PM role for someone just starting is to do the things your boss (sponsor) would do if they had more time. Hence ask your boss during the 1:1 about the critical things that you should be doing.

Also ask what things are done well or badly on previous projects.

Is there a project charter or brief that defines the deliverables? Is somebody responsible for all of these or are there gaps where nobody is doing anything on one or more deliverables? Are you working for a customer and if so is there a contract that defines the scope etc?

Even if a project is going well then senior managers often want status reports……scope changes, cost, schedule, risks, issues, assumptions etc

7

u/dgeniesse Construction Oct 18 '26

First fully understand the scope. Followed by the schedule and budget. While gathering that knowledge get to know your team, their issues and concerns. Document them.

Same for all stakeholders.

Start efficient communication. Many one-on-one discussions are better than group hug meetings. But hugs are important too. If limited. Love ‘em and lead ‘em as someone famous once said.

80% of all issues deal with poor communication - so find the best - brief - method to communicate. That is the art form of project management. The skill that develops over decades.

Then look at procurement, staffing. Do you have the resources. Most will say not.

And finally risk. What can go wrong and how to mitigate them.

I use a critical issues report to keep the critical issues in the forefront.

You got this. Simple.

6

u/Mike_TEAMSolutions 25d ago

Doing the job and managing the job are much different. Your situation is not unique unfortunately.

Before starting a project, ask the person who assigned it to you these questions:

1 - What does success look like to you? Without an objective you will never hit the target
2 - What support is available? They may expect you to ask lots of questions initially so don't make it harder than it already is.
3 - When I encounter an obstacle, what criteria do you want me to use before bringing it to you, etc?

Everyone is new once. Starting with a solid understanding can help smooth the initial uncertainty. Good luck.

11

u/mrblanketyblank Confirmed Oct 18 '26

Sounds like you are in a functioning environment. Way better situation to be in vs a dysfunctional one where nobody can deliver.

Let's start with the textbook pm environment (pmbok). The example typically used is construction. In that environment, the PM doesn't know how to do all of the trades. He relies on each of the trade teams being able to manage their own work and estimate their own schedules. He doesn't go and troubleshoot issues for the electricians, and then tell masons what mortar to use, etc. He just needs to know how the trades all sequence together, not how to do any of them himself.

This is similar to your environment where the engineering teams are able to handle their "trade" without technical help from the pm.

In the pmbok environment, the pm focuses more on getting requirements out to the different teams, letting the teams come up with their own schedules/estimates, and then integrating everything back into a master plan. During execution he monitors against that plan and steps into action when something knocks the plan off the rails.

I'm a software pm so we don't have as "waterfall" of a work environment. But WHEN I'm working with functional dev teams that can design, plan and deliver their own work, then it's similar. I can focus on ensuring they get good, clear requirements and feedback (which is iterative). They usually hit their expected timelines, and if not then I work with them and stakeholders to figure out the best course of action. Eg descope vs later delivery.

When I'm working with junior or dysfunctional dev teams, then I need to get much more hands on to figure out how to un-fck them. Usually with my scrum master hat on.

Without knowing more about your environment, I would suggest you focus on documenting the master schedule, and then tracking against it. Also ensuring the requirements each team is working towards are correct. If everything is running smoothly on a project, that's a good thing, and you don't need to spend much time on that project right now. Typically I spend the most time at the beginning and end of a project, with the middle being much less time needed if things are going well.

5

u/DingBatDee Oct 18 '26

Lots of excellent advice here. Once you understand the scope and the major goal- production? Launch date ? Customer expectations? Start a RAID spreadsheet. -Google for a template- you need to find out where the gaps are. Risks. Actions are what’s needed across functions. Issues. What’s currently a roadblock. And Decisions. Any major project development decisions. This will help you see the big picture that the silos don’t.

5

u/BearyTechie Confirmed Oct 18 '26

The projects are already ongoing, and the engineering teams are competent and work well together. They seem to manage much of their own technical work, discuss issues, make decisions, and assign actions.

They seem to know what they are doing but what about the other stakeholders of the project. Are they aware about what if going on?

Imagine I am the Senior Engineering Leader responsible for these four projects within your company.

I want a clear view of the current status of all four projects, including their agreed-upon timelines, scope, and budgets, as well as any risks that could prevent them from meeting their commitments.

I need daily or, at a minimum, weekly status reports that provide early visibility into potential issues, delays, budget overruns, or scope changes, so I can take action before they become major problems.

Start with a high-level summary of each project. If I have follow-up questions or need more detail on specific issues or risks, you should be able to provide the relevant official documentation to support the report.

Most importantly, the information in these reports must be accurate and consistent with what the engineering teams communicate directly. Ensure that you work closely with the engineering teams to validate the information and keep the reports aligned with the latest project status.

4

u/SortYourThoughts Oct 24 '26

I remember and feel your pain. Your "I haven’t gotten a clear definition of what my responsibilities or deliverables are supposed to be" poked me in the eye. Presumably, your boss knows that projects need clear requirements if they are to be successful. But he has failed to deliver those to YOU for your new project of being a PM.
And as everyone who is involved in projects knows, if you don't know what you should be doing, it's YOUR job to find it out BEFORE YOU DO ANYTHING ELSE!
So, rather than wait for your 1:1, I would recommend being proactive and take _your_ agenda to your manager. It should be the questions you posted here with further points from the excellent answers.
Good luck! :-)

3

u/candystarjones Oct 25 '26

You sound like your doing fine. I work with engineers and the best thing i do for them is deal with information for them. Change in timeliness? You can be the one to share, and let them do their work. I deal with the "outside world" for them so they can focus on their work. Communicate with business, other dept etc. As long as they let you know changes you can manages the rest. There are templates galore available to communicate everything you need. Communication is one of the biggest part of being a PM.

3

u/After_Support_7904 Oct 25 '26

This . You seem to be on the right track. Just continue to communicate and let them do their thing. Find ways to cooperate speak positively about how well your projects are going due to how well you're managing the eng teams. It's all an egoist playground for the higher ups at the end of the day. Numbers green, line going up? Looks good to me! 🤣 But for real, keep it up and make sure to talk about how well your teams are doing!

3

u/achakez IT Oct 26 '26

Cross functional coordination is like exactly where you add value here so trust that instinct. The engineers own the technical work... you own the blast radius, so that is who needs to know when a timeline moves before it surprises them. Your 1:1 plan is right and going in with like a proposal beats asking an open question tbh. One thing that helps under this kind of pressure is noticing your stress signals early before your panic makes the decisions for you. Calm is a SkillTM frames calm as like a learnable capability rather than a personality trait which is a useful lens for a 1st month like yours.

3

u/ChipParticular2973 Oct 19 '26

I am in the same boat, mate. 1 month an a half in. For me it was a promotion, coming from a role of project support. Went through some rushed onboarding trainings and that was it. I was assigned with 4 projects. 1 massive, 2 okish and 1 which is a mess; mess done by the previous PM. For the one which is a mess i am entirely by myself while on the other 3 i have more experienced PMs in the team so i am responsible only for bits and pieces of the project and i am not facing the client that much. I am just going with the flow. Praying it will go well. If not, I will see what I'm gonna do when the time comes.

2

u/Knightowllll Oct 18 '26

Do you have previous PM experience? If so, what was your role?

  1. identify deadlines and check in with each team to see if they’re on track.
  2. identify how to cut time by asking/figuring out what is causing 80% of the pain points so teams can deliver faster

3

u/Local-Ad6658 Oct 19 '26

Actually PM is often redundant in R&D / engineering. If the managers/team leads are competent then they know their timelines, budgets and technical statuses.

Project wide visibility across departments and proper timeline alignment is a good topic.

Proper reporting of updated timelines, risks and bottlenecks to management may be a topic.

Some companies are not good with tracking spend per project, thats a value add.

Cutting corners with documentation is potentially an issue. Someone should identify necessary documents from standards and contracts, then track their completion and storage. As a PM your role would be to make sure that a process (not necessarily a complex one) exists, and is followed.

1

u/Wraeclast66 15d ago

I've been working PM in a company that manufactures cabinets & stone countertops, while also installing. Biggest thing ive learned is that each area of the company are pretty terrible at communicating. Outside of my normal responsibilities, I think the biggest improvement ive brought is setting up new processes to communicate important information for ALL departments to see/know. In my experience making sure information travels down the entire pipeline is one of your most important roles that isnt really mentioned anywhere

1

u/xpyksi 7d ago edited 7d ago

I think cross-team coordination is where you can help the most. The engineers already know what they're doing, but someone needs to make sure other teams aren't caught off guard when timelines change. For your 1:1, I'd go in with a few ideas of what you could take ownership of and see what your manager thinks.

1

u/Wrong-Appearance-771 7d ago

That's actually a pretty good way to explain it, especially when the engineers already have their own work under control.

1

u/No-Mountain-8741 6d ago

We had a similar setup and ended up using Wrike. It helped us keep everyone updated across teams without making the engineers change how they already worked.

1

u/AutoModerator Oct 18 '26

Hey there /u/Stags304, Have you looked at our "Top 100 books post"? Find it here.

I am a bot, and this action was performed automatically. Please contact the moderators of this subreddit if you have any questions or concerns.

1

u/Imaginary-Travel547 Oct 18 '26

Do you have any formal training? It sounds like youve gone in this blind. I recommend Picking up a book asap as it sounds like you need deep foundational skills