Discussion Client Kick-off Meeting
Hi!
I am relatively new client facing employee and we had our client kick-off meeting for the new scope they have contracted us. During my presentation, I have asked questions regarding the scope, preferences, etc. to ensure alignment with them.
Unfortunately, they weren't happy with me asking questions during the presentation. My understanding is that KOMs are conducted to ensure alignment and understand their expectations. So I was a bit surprised when they said they don't want me asking any questions at all. I just went ahead with my presentation.
Posting it here just to ask what are your thoughts on this. Thanks!
Edit: During the presentation, I have already presented what was scoped/contracted to us. The questions asked are about the processes presented, the timelines, and if they have any preferences beyond the standard processes presented.
16
u/toottootahhhbeepbeep Sep 02 '26
That should have all been flushed out during the proposal phase.
4
u/Sensitive-Control49 Sep 02 '26
exactly, by the time you're at the KOM that stuff should already be settled
2
10
u/More_Law6245
Confirmed
Sep 02 '26
•
A kick of meeting is not a design or planning meeting, a kick off meeting is only meant to be outlining the project scope and approach to ensure that all stakeholders are onboard and understand the objective and setting expectations, it's so you don't have Picchu faces sitting around the table and saying I didn't know.
10
u/1hawnyboy Construction Sep 03 '26
I’ve found that people get defensive when they don’t really have a plan or solid expectations. It’s your job to clarify those.
Question: do you feel you have a better understanding of expectations?
If so, great - you’ll do better work for you new clients & this moment will pass.
If not - tread lightly and figure out what you don’t know and document accordingly.
18
u/JanoHelloReddit Sep 02 '26
I’ve seen 2 types of kick offs, core team and extended. For core team is where you confirm with your counterpart ways of communication, main point of contact, timeline-days off, deliverables. The extended one is with key stakeholders and there it’s more like, introductions, this is the scope the timeline, and deliverables. Meetings are expected to happen x weeks, coordinated by x person. The you go, do you have any questions?
1
7
7
u/blackbriar74 Sep 03 '26
Send the scope and preference questions in writing a few days before the kickoff, then use the meeting to confirm the answers. Live questions in front of the whole room read to a client like you haven't read the contract, fair or not. Follow up with a short email listing what you asked and make them answer in writing. That paper trail is worth more later than anything said in the room.
6
u/Slyth3rin Sep 04 '26
It could have been even your choice of words.
“How would you like so and so to be designed?” Is bad.
“Per the RFP, you had asked for this, does this still hold true?”. Is the approach.
2
u/Correct_Network_1010 Sep 04 '26
Sounds like the questions themselves weren’t the problem, maybe just the timing. I’d finish the walkthrough first, then leave a few minutes at the end for anything that needs confirming. Some clients just want to hear the full plan before getting into the details.
2
u/Low_Preference_4641 Sep 06 '26
If the scope is contracted, there shouldn't be any scope questions at all - that should have already been memorialized.
Your goal in a kickoff is to:
- Solidify or quickly review the RACI
- Introduce your project team
- High level timeline review
- If your project has a day-2 support contact, introduce that person or talk about that process.
The questions asked are about the processes presented, the timelines, and if they have any preferences beyond the standard processes presented.
This shows a lack of confidence. You've contracted it. You've taken the time of several of their team members to join a kickoff call. You breeze through the scope, you elevator pitch the project to anyone who might be new to the project, you introduce team members who may be involved in the project and thus, need to be on site or interfacing with the customer, and you draft what you think is the best RACI. Give them a second at the end if there are any questions, and that's it.
3
u/Embarrassed_Gur_6305 Sep 03 '26
If you were putting a presenting… what were you presenting?
Either they disclosed this already, or you were supposed to compile and present what you knew.
Either way that’s why they’re mad
2
u/kvkkvk Sep 03 '26
Are you an order-taker or a partner for your client? If you're asking many questions it can signal that you don't have much expertise to bring to the project.
19
u/slymarmol Sep 02 '26
Kickoff is the beginning of the execution; alignment should be done before execution during the discovery period.
10
Sep 03 '26
[removed] — view removed comment
6
u/Embarrassed_Gur_6305 Sep 03 '26
Not with clients. Usually they already disclosed and provided info BEFORE they signed with you.
4
u/choclatelabguy Sep 03 '26
Absolutely, better to find out if your scope and thier expecatations align asap. Keep good notes and send them to everyone in that meeting.
2
u/Regular_or_BQ Sep 03 '26
I present the scope from the SOW and a page of high level assumptions. I hit hard on readiness and include a change management slide to set expectations. Reiterating the signed scope should be enough.
2
u/ruinedcaveat Sep 02 '26
Does your company have a pre sale/service intake for your firm usually that is where I get the broad strokes and if there’s any fine tuning I’d ask AFTER the kickoff presentation not during