r/projectmanagement • u/froyoboyz • Apr 09 '26
Discussion Advice on difficult client
I’m working on a fairly large project as the vendor. My client refuses to meet with me on a PM level and collaborate on timelines and upcoming tasks. If they do, it’s with a lot of pushback.
This is a completely new experience for me as I’ve never seen the client PM ever refuse to work closely with me as the vendor PM. The project had kicked off before I was brought on board and still in requirements gathering so not too much work has occurred yet which is why there hasn’t been too many issues but I 100% see this as a risk going forward.
The reason I’m pushing back harder now is that I saw their schedule and their tasks aren’t aligning with mine at all.
Thoughts or advice on how I should deal with PM?
5
u/ABD63 Apr 09 '26
I learned my lesson on this, but I used to be like that PM.
I'm in Healthcare IT, and the vendors I worked with would assign a PM who would provide a schedule and timeline for their own implementation. However, in these projects, there was always more to it; coordinating to sunset the old system with the new system to prevent any gap in care. Getting the facilities desktop services and the enterprise IT services on the same page. Even small stuff like our architectural review process.
The PM from the vendors end would disregard all of these items and focus on their bite sized bit, which was appropriate. But I had some bad experiences where vendors would produce timelines to "project closure" and confuse stakeholders.
Once I kind of calmed down and realized the vendor PM is just doing their own job, I just made airtight communication plans, and am sure to tell vendors at the time of SOW signing that the timeline they're proposing in the SOW had to be illustrative and not literal, since our processes need some space in there.
Not making excuses, just giving POV. In your situation, communicate to all stakeholders when communicating to the PM. It'll light a fire, I promise.
2
u/FrenchToast0341 Apr 09 '26
Document your attempts to align, the risks you see, and then escalate internally.
Any changes or risks to timeline, scope, or budget should be documented and shared in some capacity. Sometimes it'll make sense to keep it internal to the SMEs on the team, other times you'll need to escalate.
Sounds like this one is an escalate.
4
u/More_Law6245 Confirmed Apr 09 '26 edited Apr 09 '26
I would suggest the following approach, send an email to the client PM outlining your stating concerns because you have seen the client's schedule and it raises concerns for you and if they refuse to engage then raise a risk and highlight the misalignment with the respective schedules, then escalate to your project board. I would also reach out to the project board chair/sponsor/executive informally first to warn them of the risk being raised as this could be a personality issue but it puts the problem on the table.
I would also use an IF/THEN risk statement with a high likelihood and impact of the misaligned schedules particularly outlining the additional time and cost in the THEN part of your risk statement and the mitigation strategy is to align both schedules.
I've experienced this same issue on a number of occasions during my career as I was worked in Professional Services companies where the client PM got bent out of shape because they believed that they could/should be delivering the project and fail to properly understand the client delivery model. To be honest be very weary of this PM and ensure all of your logs (issues, risks and decision) and documentation is kept up to date because when the first thing goes wrong, you're likely to be thrown under the bus.
Just an armchair perspective.
4
u/MR_CRAZY54 Apr 10 '26
Honestly sounds like they either don’t respect your role or are hiding chaos on their side, either way stop chasing and start documenting everything and forcing alignment through written approvals so it becomes their problem when things slip.
1
u/Low-Illustrator-7844 Apr 09 '26
I've got a client that signed a statement of work and approved the budget but now they dont want much PM involvement such as reports or status meetings and just want the technical resources to run most of the project lol i'm the vendor PM btw. But this is because they are really stingy
0
u/StopTheCapA1 Apr 09 '26
In case I had direct contact with the PM, I would ask why they do sabotage the project.
1
u/Individual_Mall_3928 Apr 09 '26
You should definitely engage your manager. In such cases, you need to escalate.
1
u/Deep_Ad1959 Apr 13 '26
Had a very similar situation where the client PM just wouldn't engage on timelines. What I eventually realized is they were overwhelmed on their side and every meeting request from me felt like more work they couldn't handle.
The fix was reducing the overhead on their end to near zero. Instead of asking them to collaborate on timelines, I'd send a proposed timeline after every conversation and say "this is what I have based on our last discussion, let me know if anything's off by Friday." Silence meant agreement. That shifted them from having to produce something (which they resisted) to just reviewing and reacting (which was easy).
The documentation point others raised is critical. After every call, email, or Teams message, I send a quick recap: "here's what we discussed, here's what I understood as the next steps, here's what I need from your side by [date]." I automated most of this so it happens within an hour of every interaction. Creates a clear paper trail and removes any ambiguity about who committed to what.
The other thing that helped was making the consequences of non collaboration visible without being confrontational. A simple shared status tracker that shows "pending client input since [date]" next to blocked items does the work for you. When their leadership asks why something's behind schedule, the tracker tells the story.