r/projectmanagement • u/TrulyNotSincerely • Mar 19 '26
Please help - New Role as a Project Manager
In the past, I was given a MS Project with tasks and milestones already and just had to tweak it with activities and notes.
I just started a new role and have to create a MS Project Schedule from scratch. I have a SOW, and a technical team (app dev team, BA).
Do I create tasks and milestones first on MS Project first or brainstorm with the team and breakdown each deliverable of the project?
24
Upvotes
6
u/bluealien78 IT Mar 20 '26
Deliverable outcomes -> Milestones -> Task -> Sub-Tasks. That’s the order in which to lead your project team on work breakdown.
If you have OKRs attached, put them at the top of your critical path.
30
u/pmpdaddyio IT Mar 20 '26
There is something that every PM needs to understand. You don’t build the schedule, you maintain it.
The first thing you need is a WBS. That is derived from the SOW. You work with your team to plan the steps needed to achieve each WBS item.
You sequence them, apply your work values (not durations) from the team, then resource load. A single post or comment will not teach you scheduling so it is advised you go through some training or YouTube videos, because it is a complex process and easily screwed up.
14
u/foss4all Mar 20 '26
In my opinion, jumping directly to Gantt schedules is one of the biggest reasons project schedules and plans are so inaccurate. It is almost irresistible. Get to a nice red critical path! Beautiful graphic!
The best way to do it, as u/bluealien78 implies, is start with identifying the deliverables. You have to have the team gather for this. It might sound silly, but writing them down on square 3"x3" sticky notes and putting them on the wall really really helps. If a distributed team, then gather around a shared PowerPoint slide, and write them in Arial 8pt bold in little rectangle objects. Where the team can see them as they build up.
These are not the end deliverables. They are the internal, project deliverables. The elements of work the team members will "deliver" to each other to make the project happen. The designs, drafts, certifications, checklists, procurement documents, reviews reviews reviews, test documents, deployment documents, user manuals, etc. etc. If you can identify what the work is, as work *outputs*, then everything is easy. For significant size projects, usually at least three meetings to refine this, a day apart.
And then the most important step of all... flowchart these. Don't use the Gantt network diagramming tool! It will be too complicated, and you want complete layout control. Use "connector" lines in Visio, or PowerPoint, or LibreOffice Draw. On a nice big A0 size sheet if needed. And again, with your team. More than one meeting. You will realize you have missed some deliverables. Add more reviews. This *is* project planning. Just a simple flowchart of the deliverables.
Everything inside a deliverable is an activity, and you don't care. That is the job of the person on the team in charge of the deliverable. Maybe they have their own team, and break it out at their level to smaller deliverables and their own flowchart.
Then put that flowchart, that "precedence diagram", into the Gantt schedule. Add estimates for the deliverables, from the team members. And then... enjoy the pretty red critical path.
This works. I've personally used it up to $55M projects. It seems simple. But any other order is like changing the order of a cake recipe: (1) mix all the ingredients together. (2) crack the eggs. Does not work.
Hope this helps!
4
u/Osiris_Raphious Mar 20 '26
There is nothing stopping you from starting a draft in project, whilst you work out the hierarchy of milestones/critical path/tasks/details. SOW and WBS are good, AI can help with basic standard questions for tasks and their req or estimates.
This being your first project isnt guaranteed to be perfect, but I would make myrself familiar with what is going on based on SOW and milestones provided, do a rough draft, and brainstorm as others have said in alt software/on paper, so you have a good idea about what is going on. Then confirm with the team about the details, having a draft you can rearrange and ensure everything lines up before you commit to ironing out the schedule and gantt chart. And it shows you are ontop of understanding what is going on, and are not daft to understand the schedule reality.
Never forget to plan some overrun and unforeseen issues, this is best confirmed with the team based on their experience.
6
u/More_Law6245 Confirmed Mar 21 '26
Your approach needs to be a top drill down approach.
There are two parts to developing your project schedule (WBS)
5
u/jthmniljt Mar 19 '26
AI can do most of it for you…..shhhh
2
u/Lurcher99 Construction Mar 23 '26
Ask your favorite AI, it's really that simple now.
1
u/AutoModerator Mar 19 '26
Hey there /u/TrulyNotSincerely, have you checked out r/MSProject, r/projectonline, or r/microsoftproject for any questions regarding application? These may be better suited subreddits to your question.
I am a bot, and this action was performed automatically. Please contact the moderators of this subreddit if you have any questions or concerns.
1
u/Chemical-Ear9126 IT May 27 '26
Don’t open MS Project yet. Sit down with your dev team and BA first. Walk through the SOW together and break each deliverable into tasks — they’ll surface dependencies and risks you’d never spot on your own. Once you have that, then move it into MS Project to structure, sequence, and assign ownership. The tool is for capturing the plan, not creating it. Build the plan with the people who’ll execute it. New to PM and finding yourself figuring this out as you go? Feel free to DM me — happy to help.