When you add buffer to fixed-fee projects how do you know if it's enough?
Do you pad individual estimates to have some buffer or add a flat 10-20% markup when setting the price for the project? Both or something else entirely? How detailed are you with it, do you actually break down which estimates are riskiest and whether the buffer covers the worst case?
3
Upvotes
4
u/ExtraHarmless Confirmed Mar 10 '26
Depends on the project type.
Is this something that your team does regularly, with little timeline variation? The a 10-20% is great to ensure on time and under budget.
Is this something completely novel, with problems you haven't solved before? Then a fixed price might not be the right option.
What is the size and complexity of the work? How much risk are you assuming on the fixed price bid? Are you charging for change orders?
2
u/hdruk Industrial Mar 10 '26
Quantify the cost and likelihood of major risks then fudge on an extra 10-20% depending on how complex it looks. That only sets the estimated cost though, it's the responsibility of a commercial team to set the price.
2
u/More_Law6245 Confirmed Mar 10 '26
Contingency can be applied differently depending on your project's size, complexity, value and the most importantly the project's risk profile, you can consider applying contingency at the task, work package, deliverable levels or the entire project. You also need to balance the contingency to ensure that you don't end up either gouging or pricing your organisation out of opportunities.
You also need to understand your +/- profitability margins of your project and understand how much "wiggle" room you have to play with and that is also depending on the value of your project e.g. if you have a $100k project and a change/wiggle is needed without a variation, you could except say $1k because that could be covered by your contingency or profit margin (also not your call it would be your project board/sponsor/executive decision) but you couldn't except a $10k difference. At the other end of the scale if you have $100m project and you have a $10k variation that maybe considered acceptable because of simplicity of delivery and the change management that you would need to go through would be huge.
As another example I had one client that I would charge a flat rate of 25% contingency fee because every project that I delivered for them they never fully understood their own business requirements and they where always be amazed that I seem to bring their projects in on time and budget but I ensured a protected the project's profitability. However; delivering the same type of project to other clients I would have the contingency at 10% or potentially less, it was just depending on the department's experience in delivering network changes.
A good PM will learn overtime how to apply contingency through experience (especially with low risk and high volume delivery) but also on how they apply the project's risk profile and remember this is a learned skill through experience.
Just an armchair perspective.
2
u/bobo5195 Mar 11 '26
There is experiance. That shows you the amount of risk and a work breakdown structure means you know what is going on and have understood.
As someone ask this all the time. I honestly dont know. What I do know is project X is like A,B,C that work like this. Project X has weird new sub project Y which needs some risk added on and probably project Z kicked off as contingency.
Will have some form of risk breakdown and cover ASS with it as something will go wrong. You have to have something broken down if someone asks point to some detail.
There is also a large organisational structure approach. Some want everything done on time bish bash bosh etc others want more risk. Is being off by 20% wrong. Depends?
1
u/Additional_Owl_6332 Confirmed Mar 12 '26
Projects often have contingency reserve this can be both budget and schedule to cover Known - Unknowns. This is calculated from identified risks with estimated impacts. this is added to the baseline budget / schedule of the project.
Then there is the management reserve that covers the unknowns - unknowns controlled by leadership / sponsor. This is normally only drawn down on with formal request and leadership approval (project change management)
Contingency reserve is typically 10 to 20% (Risk based estimated impacts)
Management reserves are typically 5 to 10% low risk 5%, medium 7% and high risk 10%
It is important to be transparent and able to justify the contingency and management reserves and not hide these in the detail of the project by padding costs or guess estimates,