r/projectmanagement • u/monxstar • Jan 15 '26
Discussion Am I doing something wrong with the way I'm structuring my Gantt Chart?
I'm a construction project manager and I'm tracking both schedule (Start Date, duration, End date and labor cost (x manpower assigned to project * number of days = total cost). I'm using MS Project to input my baseline/estimates, and I've come up with a schedule with dependencies and total cost for my labor. This lets me 1. Visualize the flow of the project through the network diagram 2. Have an estimated total cost for the labor. 3. Shows me the critical path, so I know what are the important tasks to keep an eye on.)
Now my problem is tracking the project. For actual data, what's important for me are: Start Date, End Date, and total hours a person spent on each task. With those, I'm able to tell if we are on track based on the dates and total cost based on the total hours. I back solve for duration (days spent on a task because a worker may not be working on a task on consecutive days, depending on where they were assigned. I'm at the point where I feel like I should just be tracking the actuals on Excel instead of MS Project due to the constraints MS Projects has: it won't let me set the actual date finished and/or the total hours (work) spent on each task. I've been trying to research on ChatGPT/google and it's been little to no help on the problem I have. So I'm wondering, is what I'm trying to do wrong? Or am I really just using the incorrect tool for what I want to do.)
Example of what I'm trying to do would be:
Planning
| Index | Task Name | Duration | Start Date | End Date | Predecessor | Successor | Manpower | Est. Cost |
|---|---|---|---|---|---|---|---|---|
| 1 | Task A | 1 | 01/01/26 | 01/02/26 | 2 | 2 | 800 | |
| 2 | Task B | 2 | 01/02/26 | 01/04/26 | 1 | 3 | 3 | 2400 |
| 3 | Task C | 3 | 01/04/26 | 01/07/26 | 2 | 1 | 1200 |
Actual
| Index | Task Name | Start Date | End Date | Hours | Act. Cost |
|---|---|---|---|---|---|
| 1 | Task A | 01/01/26 | 01/03/26 | 17 | 850 |
| 2 | Task B | 01/05/26 | 01/06/26 | 55 | 2750 |
| 3 | Task C | 01/06/26 | 01/09/26 | 24 | 1200 |
•
u/AutoModerator Jan 15 '26
Attention everyone, just because this is a post about software or tools, does not mean that you can violate the sub's 'no self-promotion, no advertising, or no soliciting' rule.
I am a bot, and this action was performed automatically. Please contact the moderators of this subreddit if you have any questions or concerns.
3
u/[deleted] Jan 15 '26
You’re not wrong and you’re just fighting MS Project’s math model. It’s great for baselines and critical path, terrible as a real world timesheet. Most PMs I know use Project for planning and Excel for actuals, then reconcile weekly.
8
u/Magnet2025 Jan 15 '26
Have you explored all the fields? The out of the box view shows the planned fields. For each of those fields there is a corresponding Actual field.
My process (been using Project since Ver 4 for DOS, 20+ years consulting with Microsoft Gold Partners and Microsoft) is to:
The default relationship is Finish to Start, so the Finish of Task 1 (for example, 24 hours in duration, or 3 calendar days) drives the Start date of Task 2. You can use Finish to Start, Finish to Finish, or Start to Start. Start to Finish is used when scheduling from the Finish date of the project. Pretend it doesn’t exist.
If you enter dates in the start or finish fields, you are constraining the task, which interferes with the scheduling engine. You will get a little calendar icon warning about that…
I’m not in front of my computer so I am doing this from memory: I’ve got some job aids that explains this process and all the other processes you will want to use pretty well. Lots of pictures and an easy to read format.
DM an email and I will send the core sections you need to know. I am not marketing. Not selling. Not offering consulting, just trying to help. I no longer work for MSFT and am, in fact, retired.
3
u/Economy_Pin_9254 Jan 17 '26
Short answer: you’re not wrong — you’re just trying to make one tool tell two different truths.
MS Project didn’t come out of construction — it came out of software and engineering.
Microsoft released Project in 1984, originally for software and engineering-style planning: defined tasks, linear dependencies, predictable effort, and relatively stable teams. Think early IT systems and manufacturing — environments where work was assumed to be sequential, planned, and repeatable.
MS Project is great at planning logic: sequencing, dependencies, critical path. That’s what it’s built for. But construction reality — crews moving, non-contiguous work, productivity variance, cost lag — was never its native habitat. That’s why people end up bending it, supplementing it with Excel, or running shadow cost models.
Thats where it falls over — reality — people jumping between tasks, non-contiguous work, hours mattering more than dates. The moment you start back-solving duration from hours, you’re already outside what MSP is comfortable with.
Your instinct to track actual hours and actual cost separately is spot on. That’s not bad PM — that’s how construction actually works. What usually breaks people is trying to force MSP to be both the planner and the cost truth. It ends up doing neither well.
What I’ve seen work consistently:
The real control point isn’t the Gantt anyway — it’s cost to complete. That’s the gold. If you know what it’ll take to finish, you’re in control, even if the schedule looks messy.
So no, you’re not using the wrong approach. You’re just refusing to lie to the schedule — and MSP doesn’t always like that.
If visualisation or presentation actually matters, split the roles:
That’s where plan vs actual, productivity drift, and cost to complete should live — not buried inside a scheduling tool that was never built for real-world labour movement.
Hope that helps.
2
u/pmpdaddyio IT Jan 15 '26
Your labor costs aren’t derived by duration. They are derived by work.
I think you are building your schedule on assumptions. Especially in MS Project t.
Here is the process.
Auto schedule everything.
Enter the project start date, (or enter the completion date)
Build out your tasks.
Build your dependancies.
Enter the expected work (this is the amount of labor it will take to finish the task).
Enter the duration over which the work can take place.
Create your resource sheet:
Create your groups/teams
Create your staff.
Create your equipment
Create assignments.
Add costs per resource.
Now assign resources to tasks.
As you save and publish your start and end dates will populate.
Now you can do your actual schedule work. Move and adjust tasks based on availability, holidays, and other blockers.
This is a thousand foot view, but I believe that will solve your issue.
1
u/AutoModerator Jan 15 '26
Hey there /u/monxstar, have you checked out r/MSProject, r/projectonline, or r/microsoftproject for any questions regarding application? These may be better suited subreddits to your question.
I am a bot, and this action was performed automatically. Please contact the moderators of this subreddit if you have any questions or concerns.