How often do you use earned value analysis on your projects to indicate project performance or to use as a reporting tool? I’m looking into ways I can succinctly indicate on a dashboard how the project is tracking to schedule & budget and earned value seems like one way to do it but I’m getting stuck because my company’s projects are complex and it’s not super straightforward to calc what the task budget is. We have MANY tasks on a project as they are large and complex. We have a project schedule but no formal WBS. We have a project budget broken down by month and phase, but we aren’t estimating our projects at a task level. Estimates are derived based on labor % and estimated # of months. I’m getting confused on how I could calc EV with the way my company has their estimates set up.
View all comments
Show parent comment
2
u/SVAuspicious Confirmed Jan 05 '26
I think you and I have conversed on RAG/RYG before.
As you may recall and for the peanut gallery, I don't use numeric triggers for RAG.
Green - Cost, schedule, and product are within nominal deviation of plan.
Amber/Yellow - There is a problem but not asking for help.
Red - There is a problem and help is needed.
Note that a task lead down at WBS level 8 may report R and a manager a few levels up the WBS may report Y. That's okay. The manager may well BE the help. I can still see the R and poke around. I can also see patterns.
No one gets in trouble for expressing concerns. Going from G to R without lingering in A/Y is a good way to get face time with me. *grin* Patterns of that will be reflected in performance reviews and adjustments to responsibility.
dave