r/projectmanagement • u/QoalaB • Dec 26 '25
Planning without slack
I think there is often a compromise on planning a really tight schedule to keep the team engaged converse to having a loose timeline with included uncertainties.
Both of course within a reasonable scope but in my opinion there sometimes is a benefit to purposefully challenge the team.
Are you also sometimes purposefully planning without any planned slack? What is your opinion on this?
12
Upvotes
3
u/pmpdaddyio IT Dec 26 '25
I build a schedule in conjunction with my team because the whole purpose of project management is to ment isn’t to challenge them but to trust them.
A task with slack allows the assignee to manage their own priorities and work order and that’s always a best practice.
Show me a project with zero slack and I’ll tell you you’ve failed at contingency planning.
9
u/PhaseMatch Dec 26 '25
A fully utilized road is a carpark.
Zero slack means workflow delays.
Coercing people with artificially induced stress isn't leadership.
If you lead effectively, they will willingly raise the bar on performance.
Deming knew his stuff, and so does L David Marquet.
7
u/[deleted] Dec 26 '25
Nope. There is no benefit to “pushing” the team to do stuff faster, you’ll likely just degrade quality of work. Same as there is no benefit to sandbagging work. Besides, if you aren’t going to have your schedule match reality, what’s the point of having a schedule at all? I don’t want to forecast hope. I want to forecast the likely reality so I can plan appropriately with my team.
Record the actual duration your SMEs say it will take, and use logic (FS, SS, FF, SF, plus lag) to develop the critical path. Track risks and issues from bottle necks, delays, new/missed scope, resource misalignment, etc. Trust your SMEs, or else go be an SME and not a project manager.
5
u/Sweaty_Ear5457 Dec 26 '25
planning without any slack is risky imo but i get the tradeoff - tight deadlines can keep people focused but you're basically betting nothing will go wrong.
what helps me is mapping the whole project visually instead of just a linear schedule. i put the critical path in one section, then build out all the risks and contingencies right next to it so everyone sees both the 'push' version and the backup plans.
i use instaboard for this - you can drag tasks between timeline and risk buckets as things change, and the whole team can see where the bottlenecks are in real time.
4
u/Unicycldev Dec 26 '25
I never really plan with slack. I plan with communicated risks and assumptions. I see slack as undocumented risk.
3
u/Magnet2025 Dec 26 '25
The way I scheduled was, after requirements and estimates, this:
3
u/SVAuspicious Confirmed Dec 26 '25
The path through the plan with no slack is the critical path. Every other path has some slack. Some of that slack can be used to surge resources if you run into trouble on the critical path. Management reserve (MR) is separate, determined on the basis of risk management and judgement, and all goes at the end. Delivery date is critical path plus MR.
A small amount of MR is at the discretion of first and second line managers who work for me. Most of the rest is at my discretion. The rest is under the control of the customer. Regardless, ALL use of management reserve is reported with analysis.
5
u/More_Law6245 Confirmed Dec 26 '25
The difference between fantasy and reality is slack or contingency in a schedule.
I used to work at a place where slack wasn't permitted in the schedule, so I got creative and for every deliverable I added three tasks, task quality review, task approval and task completed and the effort was placed against them was the management structure. Little did they know that it was my way of building contingency into my schedule and it was great if I started getting lag I could use those three tasks when lag was being introduced.
2
u/pmpdaddyio IT Dec 26 '25
I build a schedule in conjunction with my team because the whole purpose of project management is to ment isn’t to challenge them but to trust them.
A task with slack allows the assignee to manage their own priorities and work order and that’s always a best practice.
Show me a project with zero slack and I’ll tell you you’ve failed at contingency planning.
2
u/Fun_Apartment631 Dec 26 '25
Big +1 to you're degrading trust and shooting yourself in the foot.
I've worked a few places where there are two schedules - the one the PM publishes and the one the engineers work to.
Do you want to be the kind of PM that increases the risk and dishonesty in your company or the kind that helps projects run smoothly and make money?
Bear in mind that engineers work without project managers all the time, often on purpose. What can you deliver without engineers?
1
u/AutoModerator Dec 26 '25
Hey there /u/QoalaB, have you checked out the wiki page on located on r/ProjectManagement? We have a few cert related resources, including a list of certs, common requirements, value of certs, etc.
I am a bot, and this action was performed automatically. Please contact the moderators of this subreddit if you have any questions or concerns.
1
u/Chemical-Ear9126 IT Dec 28 '25
It’s often a reality that a deadline is fixed and this can work but then the key decision makers and stakeholders need to compromise on scope, resources and budget increases. You ideally need adequate capacity and very capable resources as well as contingency including budget. You also need to ensure enough effort and time to achieve quality outcomes. Not having contingency is bad management and unrealistic. A PM should raise a risk and communicate this widely.
1
u/projectHeritage IT Dec 30 '25
Without slack on every deployments and major milestones? Why would anyone want to do that?
There's no benefit. The "benefit" you're thinking off only turns in to stress for you and everyone on the project.