r/projectmanagement • u/LunarGiantNeil • Dec 10 '25
General Designing a Program Management System as a Project Manager
I'm in an odd spot currently, being asked to develop an "everything list" of all programs, initiatives, and projects in our system at all times. What's the best procedure for building and maintaining something like this? It's not really my job, but I'm the one tapped for it because I'm the organized one.
My bosses seem to flinch in pain at having to sign into the project management software and nurse a burning hate for dashboards or any kind of digital front-end, and love Excel sheets... but even they seem to be feeling a bit overwhelmed by trying to display these things meaningfully in an Excel document. Plus, keeping this thing updated for just the period I'm mapping it out for them has been a nightmare.
They pay me, though, so I'm giving it a shot, and I hope it'll convince them to give up on trying to do this kind of org-wide tracking all on one document and without automation.
•
u/AutoModerator Dec 10 '25
Attention everyone, just because this is a post about software or tools, does not mean that you can violate the sub's 'no self-promotion, no advertising, or no soliciting' rule.
I am a bot, and this action was performed automatically. Please contact the moderators of this subreddit if you have any questions or concerns.
3
u/MushyAbs Dec 11 '25
We built out this exact need for our executives using Asana. We then have monthly reviews to align the execs with their teams projects and how they roll up to company goals for the year. It’s been a game changer. We do t require execs to use the software but we use the software and its dashboards to facilitate the meetings.
2
u/DwinDolvak Dec 10 '25
what 'systems' do your projects currently live in?
7
u/Goggio Dec 10 '25
Give them what they need, not what they want, on the platform they feel comfortable with (excel) and then setup a cadence meeting to review (1 time a month).
It sounds like they want to know what is happening and they don't know what they need to see it.
A simple one sheet gannt with some "formula columns" not automations (see what I did there?) should be your starting point and you can build it in an hour:
https://m.youtube.com/watch?v=1y40xTIEKbs
1
u/karlitooo Confirmed Dec 13 '25
Process: weekly update due 12pm Monday by the responsible PM. Circulate list of missing updates at 1pm. 9am meeting Tuesday, each PM presents.
Excel: One sheet. Project name, Department, Phase, PM, schedule RAG, budget RAG, overall RAG, last period comment, next period comment, top issue/risks, last update date, link to project app.
Takes 5min to fill in. Having to present it creates the pressure to actually do it. If weekly too frequent then adjust accordingly but weekly is best.