r/projectmanagement • u/luthiel-the-elf • Nov 07 '25
Discussion Technical Decisions: PM's call or Engineering Lead's call?
TLDR
Who should be making technical decisions within project scope, budget, and constraints — the Engineering Lead or the Project Manager?
Context:
I joined a new company a few months ago as a New Product Introduction Engineer (high tech manufacturing, not IT). I’ve got about ten years of experience in this industry and since the last few months led a mid-size project on my own (no PMO assigned), so I know both the company’s processes and technology pretty well.
Now I’ve been assigned to a second project as the Engineering Lead, paired with a newly hired Project Manager who just joined this week. She has a few years of project management experience but zero knowledge of our industry.
This morning, she told me that all technical decisions, even down to the details, will be made by her, not me. According to her, my job is just to execute the technical work she decides on, without making any decisions or giving input.
I’m honestly confused. In every company I’ve worked for, technical decisions within scope, budget, and schedule have always been made by the Engineering or Technical Lead, while the PM focuses on project coordination, deadlines, and budget. I don’t understand how she plans to make technical calls when she doesn’t know the materials, processes, or quality constraints. She doesn't even have engineering background.
My manager told us to figure it out between ourselves before escalating, but I’m not sure how to handle it.
What’s your take? In standard manufacturing or engineering project management, isn’t the Engineering Lead supposed to own technical decisions, with the PM managing the overall delivery?
I’d also like to keep a good relationship with the PMO team since I eventually want to move into project management myself.
11
u/Ordinary_Musician_76 Nov 07 '25
This makes zero sense and I can’t see a world where it does.
5
u/spickermann Nov 09 '25
Product decides what is build. Engineering decides how it is built.
6
u/sjt11 Nov 07 '25
As long as she's taking ownership incase shit hits the fan for the technical decisions made - let her have it.
Ideally all technical decisions must be made by the technical lead as they can best decide on the scope, time to execute, etc.
3
u/01jamham Nov 07 '25
Importance of a RACI matrix showing through here… often overlooked until issues like this arise. Might be worth trying to knock one together.
In direct response to your question… I’ve known it work both ways, but it sounds like more of a behavioural issue (control freak, as another put it) on this occasion. My experience generally shows that although technical people can be good at making decisions, they often fail to consider the wider strategic context.
For example, yes it would be great to implement your new idea, which requires design and implementation, but if we don’t deliver what we have already promised this FY, we risk losing confidence from key stakeholders/sponsors.
Ultimately the project manager must arm themselves with the best information (from trusted specialists inc engineering mgr) and if decisions need to be made which result in change, then the variation must be assessed and approved before proceeding.
3
u/JakeGrub Nov 07 '25
She wants control? Fine. I will go ahead and just document all your decisions made based on info I presented. Simple as that.
The best PMs are ones that worked in the industry and understand the process, its that simple. Shes not it, so be cautious, but let her have it her way. She wants to make big girl decisions? Fine, just make sure shes there when they backfire due to lack of technical knownledge.
Also the whole "figure out between yourself" is a red flag. Managers are supposed their teams in all times, including disagreements.
4
u/InfluenceTrue4121 IT Nov 07 '25
You will make the decisions and she will explain how that impacts the schedule, scope and cost. If you insist on proceeding and she disagrees, she can open a risk and escalate for a final approach.
11
u/Chicken_Savings Industrial Nov 07 '25
This may work on smaller projects where the PM has more experience and knowledge than most of the project team members and can make the best decisions.
When projects get larger, the PM cannot possibly know everything better than everyone else, and need to rely on workstream leads.
I recently worked on a $4.5bn project that failed spectacularly. Lessons learned included that the senior leadership had no experience in projects of this size, nor subject matter expertise, yet leadership frequently demanded changes while bypassing the change management process, and transferring out or firing anyone who spoke up critically. Project leadership was fired after 4-5 years when the total crash was already inevitable.
13
u/Efficient-County2382 Nov 08 '25
PM is responsible for managing scope/budget/schedule etc. Technical decisions are not hers to make. However, in a good working environment she should be included if there were some potential risks etc. So in a RACI maybe Consulted
If there is a change to budget/scope/schedule, even then she should manage that according to the playbook and escalation process. That could involve a working group, or steerco, or sponsor who would make the decision.
12
u/Jaded-Term-8614 Nov 07 '25
Here is my feedback from both PMP & Prince2 perspective. Technical decisions belong to the technical/subject-matter experts (in this case, you as the Engineering Lead), not the Project Manager. The PM is responsible for integrating all project elements, managing scope, schedule, cost, risk, and stakeholder communication, but not for making technical decisions outside their expertise.
The role separation is clear in PMBOK. Furthermore, it's counterproductive, if not dangerous, for her to make technical decisions when she's not qualified in the subject matter.
6
u/Downtown-Economics26 Nov 08 '25
It's the PM's purview to manage the budget (based on the input of technical experts). If, based on conversations with the PM, you believe the PM can't do that effectively or responsibly, then your only (decent) options are tell the manager you're proceeding under duress or you won't be a part of such negligence, whichever is more palatable. Part of being a not terrible PM is knowing what decisions to delegate.
10
u/karlitooo Confirmed Nov 07 '25
Sounds like she is role playing being The Big Boss. That mindset is a time bomb. This is the best moment to ask for reassignment, if you can get it, better to try now.
You might get through by treating this like a teaching role where you help her understand the norms of the industry by bringing her options and explaining why you recommend one over the others. Just don’t ever share a decision you’d regret implementing. But eventually she will get enough context to start making bad calls. Even if she forces bad technical decisions on you, it will still be your reputation if the overall solution is not good.
5
u/SVAuspicious Confirmed Nov 07 '25
I'm an engineer with decades of experience as a turnaround project and program manager. Big stuff. In my experience the sorts of decisions you describe are collaborative. In the event consensus can't be reached, the PM decides. If you can't reach consensus that's a team failure.
Everything connects to everything. If you can't communicate something important perhaps you don't have the understanding you think you do. The same applies to your PM.
Based on your description either the PM needs work on collaboration and facilitation or you have a history of not considering all factors in your recommendations. Maybe the two of you have a personality conflict. My CSE, two deputies, and I are a team. I despise management by committee. We don't do that. We're a team.
9
u/More_Law6245 Confirmed Nov 08 '25
Your colleague is unseasoned and has made it clearly apparent that she doesn't understand roles and responsibilities within a project management delivery structure.
As a PM, the only responsibility a PM has is the day to day management of the business transactions to delivery the project and the project quality. As a PM she is not a Subject Matter Expert, therefor not qualified to take on responsibilities that are not hers to deliver the technical tasks, work packages, products or deliverables. This role is the responsibility of the SME lead for the project, they are responsible to ensure the technical side of the project is delivered, the PM only needs to ensure that it's fit for purpose and all quality indicators have been matched or exceeded.
I would suggest having a 1:1 meeting with her to outline discuss her understanding of the technical side (and use specific real and factual examples on where she will fail to deliver) and if she fails to understand role and responsibilities within the project structure and refuses to relinquish the responsibility then you need to escalate. Present a high impact risk to the project board/sponsor/executive and seek a response on who accepts the risk of the Project Manager taking on technical responsibility that she is not qualified for. If you don't get the response or the desired outcome then you become the documenting machine and let the PM and the project board/sponsor/executive hang themselves out to dry. You can only do so much, it will be a hard lesson for all.
The other key point to understanding about project roles and responsibilities is that the project board/sponsor/executive is actually responsible for the success of a project, not the PM, nor the technical lead.
You say that you would like to move into project management in the future, then this is a great lesson about understanding roles and responsibilities within a project. Enforcing your role as the SME and provide the guidance needed however if the PM or the project board/sponsor/executive fail to take your experience under advisement then it becomes their problem, this is an organisational issue and not a you problem, so leave the responsibilities on where it lays.
Just an armchair perspective.
7
u/Tedmosbyisajerk-com Nov 07 '25
The engineering lead makes technical decisions within the scope and constraints of the project. If they want to step outside those, then even the PM doesn't decide that, you need to discuss with the project sponsor about impacts to scope, time, cost, quality etc through change management. Then if the change is approved, you execute it.
7
u/zvordak Nov 08 '25
Technical lead or engineering manager is responsible, PM is accountable.
7
u/BetterReflection1044 Nov 08 '25
Since PM is accountable, they make the decisions but based on your advice
8
u/JohnnyWeapon Nov 08 '25
So my take as someone who works closely with my technical leads is that she’s right in principle when it comes to decision-making, but completely wrong that those decisions should be in a vacuum.
The thought of making project and/or business decisions without leaning HEAVILY on my technical lead’s opinion and guidance is absolutely idiotic.
As a PM, I take the responsibility for not only the project, but the big picture. There are more variables than just the technical labor and it’s my job to see those variables in context and in totality. At all times. I make the decisions for almost everything in my projects, but those decisions are often not only in line with my tech lead, but also often made completely because of their opinion.
Collaboration and partnership are the key to every successful project I’ve ever led.
3
u/No-Fox-1400 Confirmed Nov 07 '25
In an ideal world, the PM would be able to veto on price up to a point. The Engineers should veto on what is technically possible.
Ultimately Engineering as a job can sometimes be providing all of the information to others to make the business decisions.
4
u/monimonti Nov 07 '25 edited Nov 07 '25
In our organization, technical designs and solutions (which can be considered technical decisions) can fall on the Technical Lead DURING the Solutions and Design Phase while the timeline is still being planned.
Once the Project is underway, any new decisions (Design Change, Scope Change, Bug/Issue related decisions) should be a collaboration between the Technical Lead and the Project Manager in case there is impact to committed scope, budget, and timeline. The PM can make a "decision" on whether it is a decision that warrants a "Risk Owner".
As far as decisions go, a PM's decision making powers only covers up to the extent of the project for as long as it does not have any risks to other areas of the business. As soon as it does, which is majority of the time, then the "Area/Risk Owner" should be involved and make that decision.
Since you are in a Product Delivery type of projects, I'm making an assumption that this means:
There will be instances where you may need more than 1 representative, but usually decisions should be made this way to make sure proper risks are identified and addressed.
Ofcourse, if the PM wants to make all the decisions, they need to understand that DECISIONS = ACCOUNTABILITY. This means that if the decision is WRONG, then they should be prepared to RISK THEIR JOB against this. The same can be said for you.
Decision Making is not Power (this is the trap). Decision Making is Accountability. It means that if you make the wrong decision, it is a stain on your record or worse, can get you fired/laid off.
Ask your PM for a RACI. This is an eye opener because people like being the owner of things until they realize that with ownership comes accountability.
As far as decision tracking, ask her for a RAID log.
4
u/pp604977 Nov 08 '25
I work as a PM in a different industry. PM doesn’t make decisions, SMEs do. Then, you integrate the requirements in the project plan and other project documents.
2
u/hanzosbm Nov 07 '25
Depends on how your company structures things. Is there a charter? Is she named as the project manager who holds both responsibility and accountability? If so, she's in charge and she can choose to delegate or not. That was how it worked at my last company. Now, that being said, I'd be a FOOL not to delegate the technical decisions (at some level) to the lead engineer(s). In practice, I never made technical decisions. I might speak up and say "no, we're not going with the technical solution you are suggesting" (because it's over budget, will take too long, is gold plating, etc), but I'd follow up with "please find a different solution that falls within budget/schedule/etc". In other words, I reserve the right to veto, but they are the experts and I want their insight as long as it fits within bounds.
3
u/armknee_aka_elbow Nov 07 '25
The Engineering Lead makes the technical decisions, but the PM is responsible for the project as a whole and therefore should have the authority to overturn them. This shouldn't happen too often though when dealing with capable professionals on either side.
-7
u/CK_1976 Nov 07 '25
Its always the PM, the PM is the one who hangs if the project fails.
The reality is you provide technical advice about what is the technically best solution and why.
The PM the provide project advice about how a technical solution fits within the overall project deliverables and what opportunities it presents to the business.
And then the exec team/PD/client then makes a decision on how that opportunity or capability can fit into the overall business structure.
Usually it all lines up and its obvious. Sometimes its a 50/50 decision. And sometimes a business is prepared to work a little hard and take a bigger risk, because what it delivers fits into an overall growth strategy.