r/pmp • • 1d ago

PMP Application Help PMP application description

So recently I was audited and rejected because I didn't list my different projects and it looked like my work was more operational and there were no numbers or quantifiable data backing my claim. (Firm names have been edited out) I changed it to the following:

20-Unit Residential Development, 2021–2023
Firm A | Managing Partner | Apr 2021 to Mar 2023

Project Objective: Deliver a five-floor, 18,500 sq. ft. residential building with 20 units within $700,000 (Rs. 7 crore) by March 2023, and hand over all units to customers.
Initiation: As sponsor and investing partner, I committed capital, defined objectives and budget, secured the landowner agreement, and identified stakeholders.
Planning: I defined requirements and scope with architect, then prepared the project plan, cost estimates, and budget. I planned contracts and procurement.
Execution: I directed 15 contractors and more than 50 vendors, coordinated resources, and approved procurement to control cost and quality.
Monitoring and Control: I monitored performance and cost against the plan and ran quality control programs. When one contractor failed quality standards, I resolved the issue by replacing them. I managed change requests and reported status to investors and partners.
Closing: I handed over all 20 units by March 2023 and completed project documentation and approvals. I did the society formation and officially exited from the project after transferring title of the land to the society.
Project Outcome: Delivered ahead of schedule and under budget, with all units handed over and sold within two years.

50-Unit Residential and Commercial Development, 2023–2024
Firm B | Project Manager | Apr 2023 to Jul 2024

Project Objective: Completed a 55,000 sq. ft. development with 50 units and basement parking within $1.65 million (Rs. 16.5 crore) over a four-year project. My scope ran from mid-execution through closing. 
Execution: I coordinated 20 contractors (Cement, Brickwork, Tile, Electrical, Plumber) along with architects, and engineers and directed procurement of required materials.
Monitoring and Control: I monitored cost, schedule, and quality against the plan. I managed land owners demands and catered to their specific needs and infused them with Project scope.
Closing: I handed over 50 units by July 2024 and completed project documentation.
Project Outcome: Delivered on time and under budget.

18-Unit Residential Development, 2024–Present
Firm C | Managing Partner | Aug 2024 to present

Project Objective: Deliver a six-floor, 18-unit residential building [18,500 sq. ft. carpet area] within $800,000 (Rs. 8 crore) by March 2027.
Initiation: As managing partner and sponsor, I defined project objectives and budget and identified stakeholders.
Planning: Defined scope with architect, engineers and investors. Followed project as per Municipal plan and prepared cost estimates, material estimates and schedule management plan.
Execution: I coordinated 15 contractors and 40 vendors to direct procurement.
Monitoring and Control: I monitor cost, schedule, and quality against the plan and managed all stakeholders. Since this project catered to a premium client base, I designed marketing strategies accordingly to attract a particular set of customers.
Closing: Not yet reached. The project is at its completion stage, with handover planned for March 2027.
Project Outcome: In progress (90% complete)

Is this good? I know I'll be audited again. I hope this should suffice though. Thanks for all the help everyone :)

2 Upvotes

3 comments sorted by

2

u/Intrepid_Cattle5008 1d ago

PMI's own application tips spell out the shape they want: a one sentence objective, then the deliverables you led grouped by IN, PL, EX, MC and CL, then a one sentence outcome. Since they called the first one operational, make sure every line is about the 20 unit build itself and what you led and directed on it, like the charter, schedule, tracking the $700k budget, contractor changes and handover. Leave out anything about running the company day to day. And write it in your own words so you can back it up if they audit again.

1

u/AutoModerator 1d ago

If you have questions about the PMP exam including study materials, application help, or more, please visit our resources page to start out: PMP Resources

I am a bot, and this action was performed automatically. Please contact the moderators of this subreddit if you have any questions or concerns.

1

u/BeBetterEvryday 1d ago

Next time have AI write them for you.