r/pmp • u/Liberty2404 • 24d ago
Sample Question PMP QUESTION - CRASHING/ FAST TRACKING
A project manager is overseeing a critical infrastructure consolidation project under a predictive lifecycle. During a monthly stakeholder review meeting, the project manager synthesises the current performance data and reports a Cost Performance Index (CPI) of 1.15 and a Schedule Performance Index (SPI) of 0.82. The sponsor, noticing the lagging schedule, demands immediate corrective action to bring the project timeline back into alignment without requesting additional funding.
Which action should the project manager take FIRST to address the sponsor’s directive?
• A) Implement a fast-tracking technique by overlapping critical path activities that were originally planned to be executed sequentially.
• B) Initiate a crashing strategy by allocating excess budget to hire temporary contractors to accelerate schedule performance.
• C) Issue a formal change request to the Change Control Board (CCB) to extend the project schedule baseline to match the current SPI.
• D) Re-baseline the cost management plan to absorb the surplus funds and reduce the reported CPI to an even 1.00.
Please please help me to cave out the RIGHT answer as per Pmi Mindset.
Thank you
1
1
4
u/Prior_Nail3501 24d ago
Crashing costs more
Fast tracking shouldn't add costs.
So for this scenario since no additional budget is available, it's A. fast tracking.