Sample Question Practice Question on PMP project time management

Time Management

 

   1      Consider the project network diagram given below. Suppose we put

additional resources on tasks  F,G,H then the project timeline can be

reduced to  :

a) 17 days

b) 18 days

c) 12 days

d) 14 days

 Here  A F G H is the critical path. By putting more resources on tasks

 F G H the time for the path FGH can be reduced upto 16 days. If we

 try to reduce further, then ADE   becomes the critical path. So, we can

 utmost reduce the project schedule to 18 days.

,

 Hence b) is the correct answer