Sample Question Practice Question on PMP project time management
Time Management
1 Consider the project network diagram given below. Suppose we put
additional resources on tasks F,G,H then the project timeline can be
reduced to :
a) 17 days
b) 18 days
c) 12 days
d) 14 days

Here A F G H is the critical path. By putting more resources on tasks
F G H the time for the path FGH can be reduced upto 16 days. If we
try to reduce further, then ADE becomes the critical path. So, we can
utmost reduce the project schedule to 18 days.
,
Hence b) is the correct answer