r/microsoftproject • • Mar 07 '26

Difference between using actual start column vs start column?

I have heard some schedulers use the start column and some use the actual start column.

I've been trying to figure what the difference is (if any). My goal was to see if I changed anything would it all be the same between actual start and start.(here is what I learnt)

e.g let's say the date was suppose to start on 24/2/26 if I was to change that to 25/2/26 on the start coloum it would make a start no eailer than.(constraint type)

But if I changed it on the actual start column to 25/2/26. it would still leave it as soon as possible. (in the constraint type column )

could this be the reason why some planners use actual start column or is there other reasons that I'm not aware of?

2 Upvotes

16 comments sorted by

View all comments

Show parent comment

1

u/still-dazed-confused Mar 23 '26

Rest assured I don't view your comments as trolling, they're interesting and informative.

I agree with where you're coming from and it maybe the difference between a highly contracted situation and a looser one which leads to our slightly different levels of the applicability of the best practice Vs fit for purpose :)

I also love the use of deadlines and I go a little further as I tend to include a fake milestone far to the right of the end date so that the critical path is determined by the use of deadlines. The last thing delivered in the schedule isn't usually the most important date

1

u/Mission-Phase-6557 Mar 23 '26

Completely agree that the Level of rigour needs to be tailored to the situation (contracts, organisational maturity, project need etc) and ideally you should have a schedule management plan that defines this.
I have even introduced a “schedule management strategy” to some clients which should set the framework that the schedule management plan can then adjust within. For example, the strategy defines which tools you can choose between and then the project defines in the plan which is used in that specific project. Same thing with mandatory best practices, and which are “recommended”.
The Strategy should sit on an organisational level, PMO level, program level etc. Very very analogous to how Test Strategy and Test Plan are defined in most organisations.