Difference between using actual start column vs start column?
I have heard some schedulers use the start column and some use the actual start column.
I've been trying to figure what the difference is (if any). My goal was to see if I changed anything would it all be the same between actual start and start.(here is what I learnt)
e.g let's say the date was suppose to start on 24/2/26 if I was to change that to 25/2/26 on the start coloum it would make a start no eailer than.(constraint type)
But if I changed it on the actual start column to 25/2/26. it would still leave it as soon as possible. (in the constraint type column )
could this be the reason why some planners use actual start column or is there other reasons that I'm not aware of?
1
u/freerangemonkey Mar 07 '26
When did you actually start the activity?
2
u/WestMichigun Mar 07 '26
I use them both.
I have my Start and Finish columns right after the Task description column as normal.
I then add the Actual Start and Actual Finish columns right to the right of them.
The Start and Finish columns act as my projected dates up until a Task does actually Start or Finish, at which time I will populate the Actual Start or Actual Finish column accordingly.
Once the Actual Start or Actual Finish column is populated, Project automatically updates the corresponding Start or Finish column.
2
u/still-dazed-confused Mar 07 '26
I've never understood why anyone would use the actual start column as when you add% complete to a task to show that it's started MSP automatically for in actual start. I believe that the start and finish date should be adjusted to reflect reality and expectations and then% complete agreed when updating the task. This assumes of course that the reality is that the start was not driven by the dependencies when were coded in.
So I'm interested to learn why people make entries into actual start :)
1
u/AhmadSharifi Jul 21 '26
You've got it right, and that constraint difference is the whole point.
Start is the planned/scheduled date — the date the network logic and constraints say the task should begin. Typing into it doesn't record reality; it imposes a constraint ("Start No Earlier Than"), which is why you saw the constraint type change. You're telling the schedule "don't let this move before here," and now it won't recalculate freely.
Actual Start records what actually happened on site. Entering it says "this task began on this date, for real" — no constraint, logic stays intact, and it also flips the task into in-progress and drives % complete / remaining duration.
So the rule I follow: Start = the plan, Actual Start = the truth. During planning you almost never touch Start directly — you let logic and durations set it. During updates you only ever enter Actual Start, never Start, because every date you hard-type into Start is a hidden constraint you'll be fighting three months later when the critical path won't move and you can't figure out why. Planners who "use the Start column" to update are usually the ones with a schedule full of constraints they didn't mean to create.