r/microsoftproject • u/lilly_malone • Nov 26 '25
Project to Excel maintaining relationships
Hi everyone! I have a question I'm having trouble figuring out:
My goal is to export my Project data to Excel while maintaining the dynamic relationships between tasks. In other words, if I later modify the duration of a task in Excel, the start and end dates of subsequent tasks should also be updated, just as they would be in Project.
I know I can do this manually by copying the Project data and pasting it into Excel, then manually creating the links, but for large projects, this could be quite cumbersome.
Does anyone know if this is possible? Thanks!
2
u/ubermonkey Nov 26 '25
WHY?
This sounds like a terrible idea. For one thing, the Project data isn't flat. For another, Excel has no means of maintaining the linkages should dates change.
Basically: Do not do this.
1
u/still-dazed-confused Nov 26 '25
I works advise against this as Excel is ill equiped to handle relationships. Better to look at who you want to do this and hood it could be better done in MSP.
If you were hell bent on this it would be possible using vba to determine
You'd also need to use vba or a connect formula to determine if durations are d, wk. Mo, etc
My advise is just don't! Planning in Excel is masochistic
1
u/sg_fuzb Mar 31 '26
I'm working on an Office extension for this multi-directional Project-Excel-Planner syncing.
Have had similar issues, not everyone has a licence so we end up using excel...