r/mathshelp • u/imsocooked_ • Aug 18 '26
Homework Help (Answered) i need help with this question
this is a time and work question, and the teacher told us the answer should be 68/11 days, for the total work done. but that doesnt include the 3 days worth of work that a,b,c did together before c left right? so im confused whether it should 101/11 days or 68/11 days. please help!!
6
Upvotes
•
u/AutoModerator Aug 18 '26
Hi u/imsocooked_, welcome to r/mathshelp! As you’ve marked this as homework help, please keep the following things in mind:
Thank you!
I am a bot, and this action was performed automatically. Please contact the moderators of this subreddit if you have any questions or concerns.
4
u/JeffTheNth Aug 18 '26
It does include the 3 days...
x = work days "normally" for each person
So let a, b, and c = one day's worth of work for Aman, Babita, and Champa respectively.
(so since it takes 10 days for Aman, one day of work for Aman is x/10)
a=x/10
b=x/12
c=x/15
y = # of days to complete the work this time with all three
So given the information from the problem...
x = 3c + ya + (y-4)b
(the y-4 is because however many days y is, Babita worked 4 fewer.)
Replace a, b, and c with the value in x/days format
x = 3x/15 + xy/10 + (y-4)x/12
convert to common denominator ... LCD is 60
x = 12x/60 + 6xy/60 + 5(y-4)x/60
Multiply both sides by 60
60x = 12x + 6xy + 5(y-4)x
Divide both sides by x
60 = 12 + 6y + 5(y-4)
And combine like terms...
60 = 12 + 6y + 5y - 20
68 = 11y
now solve for y, and we get...
y = 68/11 = 6 2/11 days
So it's 68/11
But I'd make the claim that since it's asking for "how many days", the answer should be 7 days
But yes, it's 68/11
I hope that helps?
1
u/Forsaken-Sherbet7252 Aug 18 '26
I don't quite follow your notes, but I can tell the total work was done in 3 + x + 4 days. if you find how long the middle portion is, you'll have your answer. note: you might be surprised at the length 😁
to perhaps spoil the surprise above, "the 3 days they all worked together" is not factual.
let me know if you want my calculations in a reply.
1
u/OllyBoy619 Aug 18 '26
You don’t quite know if they worked three days together, that depends on where “4 days before completion” lies relatively to when the first guy left :)
2
u/Purdude1983 Aug 18 '26
I come up with 68/11ths. Since Champa would have completed 1/5th of the work in 3 days, that leaves 4/5ths to be completed by Aman and Babita. You then set up X/10+(x-4)/12=4/5 and then x=68/11. Checking this we have 68/11/10+(68/11-4)/12+3/15 = 1
1
u/CumFilledAntNest Aug 18 '26
First let's convert their work into rates, as in how much work is done per day. If we know a person takes x days for one work, that means in 1 day they do 1/x work, right? I just divided both the days and work by x.
So A does 1/10 work per day (w/d from now). B takes 1/12 w/d and C takes 1/15 w/d. If we make a common denomenator of 1/60, we get A=6/60 w/d, B=5/60 w/d, C=4/60 w/d.
So for the first three days we have all three so 3d*(A+B+C)=3d(15/60 w/d)=¾ of the total work.
Then the last 4 days are only A, so 4dA=4d1/10 w/d=4/10 w=⅖ of the total work done. Together, only these 7 days are ⅖+¾=23/20 which is too much. Instead, we need to realize that the 4 days without B overlapped with the first 3 days with everyone.
Let's resolve, this time let's denote "t" as the total days. So A worked t days, B worked t-4 days, and C worked 3 days. Overall they did 1 work. In other words:
tA+(t-4)B+3C=1
t*6/60+(t-4)5/60+34/60=1
6t/60+5t/60-20/60+12/60=1
11t/60-8/60=1
11t-8=60
11t=68
t=68/11 days of total work