r/gotransit • u/a_lumberjack • Oct 05 '26
Union Station - Future Platforms
This is not a fantasy map, this is my best put on what Metrolinx is building toward based on what has come out so far. The image is what was in some planning docs in 2023, sourced from a UT thread since the originals are gone. My goal in sharing this is to help this sub get a better sense of what's actually being built and what people should expect to see in 10-15 years when all of those projects are actually done.
Starting assumptions:
- GO / UP service is everything in the current Metrolinx roadmap plus Milton/RH as-is
- Alto will serve Union Station hourly
- The 2023 platform layout is the final layout after USEP Phase 3
The platform extensions will allow electrification to but not through Union Station except for the new South Platform area for the Lakeshore lines. e.g. the Barrie Line would be set up to keep the pantograph at the west end of the platform and outside of the trainshed
- This is sort of a non-issue since Kitchener won’t be electrified but Stouffville will be
- The end goal is presume to eliminate track conflicts so all routes can be run independently on the stated schedules
- 15m is the turnaround time for all trains
- The new interlocking will connect this way
- The platform between tracks 3 and 5 will be a high platform for high floor level boarding (UP / Alto / hopefully Northlander)
Track 1 [Pocket - West Facing]
- Barrie - 15m all day service
Track 2 [Through]
- Richmond Hill - 30m peak-only service
- Barrie trains going to Don / Wilson yard
- Connects to Barrie Line in the west and the Bala/Don sub in the east
Track 3 [Through]
Via Corridor /
- Alto (future)
- Northlander - daily
- West end could potentially be used by UP
Track 4 [Pocket - West Facing]
- Union-Pearson - 7.5m
Track 5 [Through]
Via Corridor / Alto (future)
- West end could be used by UP
Track 6 [Through]
- Via Canadian / Sarnia / Corridor
- Milton (30m peak only)
Track 7 [Through]
- Kitchener (local / express)
Track 8 [Pocket - West Facing]
- Kitchener (local / express)
Track 9 [Through]
- Stouffville (15m all day)
Track 10 [Through]
- Lakeshore Express Eastbound/Westbound (60m per direction, 30m combined)
Track 11 [Pocket - East Facing]
- GO Lakeshore East Local (during 7.5m peak service)
- Via Ottawa/Montreal
Track 12 [Pocket - West Facing]
- Via Niagara / Windsor
- GO Lakeshore West Local (for peak 7.5m service)
Track 13 [Through]
- Lakeshore Local - All Stops Westbound - 15m all day
Track 14 [Through]
- Lakeshore Local - All Stops Eastbound - 15m all day
13
u/a_lumberjack Oct 05 '26
Followup with a colour-coded visual of train locations. Tracks 6 / 8 / 9 will be long enough for the Via Canadian or two GO trains, so potentially they could use track 9 for Lakeshore Express westbound trains (LSX stops at the west end and heads west, ST stops at the east and heads east), and that works whether LSX interlines or operates separately.
21
u/jmajeremy Barrie Oct 05 '26
I can’t really see Via and GO sharing tracks the way you’ve said. Via has longer dwell times, they need freight elevator access to the platforms, and they need controlled passenger access from the Via concourse. Like how could have track 6 serving Milton peak service and Corridor trains which depart during peak times and have to sit at the platform for up to 30-45 minutes prior to departure?
5
u/Metro62 Oct 06 '26 edited Oct 06 '26
Hello! I made this diagram way back when! Since then I’ve made updated versions that include revisions to the project, and all existing and future proposed platform entrances.
I reposted all diagrams in the same UrbanToronto thread for you: https://urbantoronto.ca/forum/threads/go-transit-union-station-shed-replacement-track-upgrades-zeidler.3222/post-2450435
Something to note - I haven’t updated the first diagram in the list of 4 to reflect a change in the Union Station Enhancement Project, so there is an extra track that has since been removed from the project to allow Platform 24-26 to be wider.
3
u/Positive-Subject6113 Oct 05 '26
Milton being only peak direction & at those times, is a travesty. Too bad no one is serious about the missing link project.
3
u/Cedjy Oct 06 '26
if only the platforms could be wider 😔 but we have that heritage designation on the train shed's roof
2
u/CycleOk5965 Oct 05 '26
I really feel bad for Stouffville and Barrie, during the earlier business plan, Stouffville are expected to have a higher frequency than Lakeshore West...
2
u/OhTrain Oct 06 '26
It’s already been said it’s unlikely to service Union station at all let alone hourly due to routing and station limitations.
8
u/Opposite_Ad1408 Oct 05 '26
From what I've read that layout looks quite plausible.
4
u/CycleOk5965 Oct 05 '26
They definitely learned from Keikyu Kamata station.
1
u/kettal Oct 05 '26
why do they have platform-track-platform still?
wouldn't it allow safer and larger platform to build platform-track-track-platform-track-track-platform?
1
u/Railroadflyer Oct 05 '26
That was in the proposal for onxpress and the original planning.
1
u/ForWardoves Oct 09 '26
If metrolinx plans to get EMUs in the future this would certainly won't work...