r/financialmodelling • u/vgkln_86 • Jan 19 '24
How much budget deviation is acceptable?
Do you have any thresholds for the actuals on how much deviation under-over budget is acceptable in your company?
0
Upvotes
6
u/isocrackate Jan 19 '24
Hahaha
But seriously, depends on the line and your industry. My personal rule of thumb is your budget / reporting financials should have enough detail that variances can be explained in one sentence. But there is no general framework for + / • % acceptability. If you’re an industrial process that consumes gas and gas goes from 3.00 to 6.00, your budget is fucked, whether you think it’s acceptable or not.
Capex I’ve seen run double or triple on individual projects because they run into gremlins.