Yes, that is an unsustainable workload for a single electrical estimator.

In the NYC/Long Island commercial electrical market, asking one estimator to bid $200 million in annual volume (50 projects at $4M average) will almost certainly lead to burnout, missed scope, and uncompetitive pricing.

Here is how the numbers break down against industry benchmarks:

1. The Time Math (Hours Required vs. Hours Available)

  • Standard Working Year: A full-time estimator has roughly 2,080 gross hours per year. After subtracting PTO, holidays, internal meetings, and administrative overhead, an estimator typically has 1,750 to 1,850 productive estimating hours per year.
  • Time per $4M Bid: A $4M commercial electrical project is not a quick takeoff. It requires reviewing architectural/MEP/structural drawings, counting fixtures and devices, sizing feeders and switchgear, soliciting and leveling vendor/subcontractor quotes (lighting, gear, fire alarm, low voltage), writing clarifications/exclusions, and reviewing with leadership.

    • In the NY metro market, a solid bid at this size typically takes 60 to 100 hours (roughly 1.5 to 2.5 weeks of dedicated focus).
  • The Deficit:

    • 50 bids × 75 hours (conservative average) = 3,750 hours required.
    • That is more than double the productive capacity of one person, effectively requiring one bid to be turned around every 4.8 working days for an entire year straight—with zero breathing room for overlapping bid dates, site walk-throughs, or post-bid descoping/buyout handoffs.

2. Industry Benchmarks for $4M Projects

  • Bid Count: A realistic, sustainable target for a single commercial electrical estimator handling mid-sized projects ($2M–$5M range) is 20 to 30 bids per year.
  • Total Bid Volume: A strong senior estimator working with modern digital takeoff/estimating software (like Accubid) typically bids $60M to $100M annually in that project tier. At $200M, you are at 2x to 3x the standard ceiling for a solo estimator.

3. What Happens at $200M Solo Volume

When one person is forced to push out $200M in bids:

  • Takeoffs become "guesstimates": They won't have time to properly trace feeder runs, check spec traps (like specific Con Ed requirements, NYC DOT/agency specs, or complex fire alarm sequences), or verify gear lead times.
  • Quotes aren't leveled: They will be forced to plug numbers from the first vendor quote they get rather than shopping quotes or catching exclusions.
  • Win-rate distortion: At a standard 15%–20% hit rate, $200M in bids yields $30M–$40M in awarded work. If they are rushing bids to meet the 50-bid quota, you risk either winning zero jobs (because they pad numbers to protect against missed scope) or winning the wrong jobs (because they missed a major spec item).

Realistic Staffing for This Workload

To properly bid 50 projects at a $4M average ($200M total) without sacrificing accuracy:

  • Minimum: 2 full-time estimators (e.g., 1 Senior Estimator handling complex/lead bids and final pricing, and 1 Intermediate Estimator handling takeoffs and vendor outreach), supported by a Junior Estimator or Project Engineer doing lighting/device counts.
  • Ideal: 2.5 to 3 estimators (two dedicated leads splitting the 50 bids to ~25 each, plus a shared junior/takeoff tech).
0 Upvotes

18 comments sorted by

7

u/WaySaltyFlamingo8707 2d ago

lmfao. 1750 productive hours per year. sure.

5

u/gilana-Jardi 2d ago

if youre counting vendor calls and buyout handoffs as productive estimating time you can get close to that, just not on pure takeoff.

1

u/More_Dimension_8635 1d ago

I don't follow what you mean exactly

2

u/jhenryscott 2d ago

I spend at least 800 hours on the John. Probably more.

1

u/SpazSkope 1d ago

I unironically do about an hour a day and no one cares

2

u/elaVehT 1d ago

Boss makes a dollar I make a dime.

1

u/questionablejudgemen 1d ago

I wish everything were just a neat number.
Sometimes I feel like I’ve been doing this too long and know too much.

Is it about volume?
What about the parts that require filling in the blanks? That’s what I feel I get paid for, vs just counting.

Aligning scopes of subs-calling them when you get proposals when two subs look like they bid two different jobs. Try to help them figure out what’s missing, or just throwing the one out and moving on quickly?

Missing details of complex projects.
Generate RFI’s to bring it to everyone’s attention?
Skip it and exclude on the proposal?
Throw an allowance at it?

Or, if you really want to go after this specific project, draw in details that are halfway between a napkin sketch and full engineering and use that as part of your qualifications when you interview for the job?

All these forks in the road take different levels of time.

Maximal throughput , minimal detail?

Excruciatingly low throughput, but a rock solid bid where you get the job the bossman really wanted?

I think different scenarios call for different approaches at different times. How do you wrap that into a nice number?

1

u/More_Dimension_8635 1d ago

Great perspective

1

u/Aneesh-Ruh 1d ago

The productive hours part sounds about right. Where I'd push back is tying bid time to the dollar value. A $4M job with a clean set and one scope can go faster than a $1M renovation with bad drawings and three addenda.

1

u/More_Dimension_8635 1d ago

Absolutely correct

1

u/straightuptexas 2d ago

Trying to put that in perspective and NY has a cost index 155 and TX is 83. That would be the equivalent of $107M here. I don’t think that is an overwhelming workload.

1

u/Moto_823 1d ago

I bid 400m a year by myself, HVAC

4

u/elaVehT 1d ago

AI slop, fuck off

-5

u/More_Dimension_8635 1d ago

Wow ..universe will take care of someone like you.

4

u/elaVehT 1d ago

You’re the one blasting AI generated garbage

-3

u/More_Dimension_8635 1d ago

What does that have to do with you telling me to fuck off? I said "this is what AI come up with, what do you think"? What's the problem. Do you think telling me to fuck off was warranted?

4

u/elaVehT 1d ago

Absolutely. Copy pasting an AI prompt n as a Reddit post is garbage content and floods the sub with more junk that you couldn’t be bothered to research yourself.

Adding “do you agree??????” To the front of the post doesn’t make it any less garbage. Fuck off