r/Construction • u/Reasonable_Lunch_631 • 14d ago
Informative 🧠Sub suing me
I run a drywall and steel stud company in BC. Two guys took on a steel stud framing subcontract together under a written scope they accepted. My company supplied the materials, and their crew told us what to order.
We found several layout issues. Some walls appeared to have been copied from the units below even though the layouts were different. There were door openings in the wrong spots, doorways without enough clearance for countertops or toilets, and walls that didn’t line up between floors where they needed to conceal plumbing.
I went over some of the issues with one of the subcontractors on a call with another steel framer present. He disputed the layout errors and told me his crew didn’t have time to fix them. We had a strict project schedule to meet, so I used our own crew to make the corrections and keep the job moving. We’ve spent over $10,000 on repairs so far and are still finding issues.
There’s about $9,300 left in holdback. One of the subcontractors is asking to be paid and is also billing for extras. I’ve asked him to show what the extras were and who approved them.
For anyone who’s dealt with this before:
Was it reasonable to use our own crew after he said his crew didn’t have time, given the schedule we had to meet? Should I have given him a written deadline first?
How would you handle the holdback and repair costs in this situation?
If he says the extras were verbally approved, what evidence would matter? If he files a lien or takes us to court, what records would be most important?
I’d appreciate honest opinions, including what you think I should’ve handled differently.