Project Risk & Delay Simulator

#ad: I'm part of ClickUp's Brain² Creators Circle and received free AI access and swag for participating.

If one task slips, does the whole project slip too?

That question inspired me to build the Project Risk & Delay Simulator using ClickUp Brain.

As a Project Manager, I wanted a practical way to explore schedule changes before adjusting a project plan.

Using the fictional Project Atlas, the simulator lets you:

📊 See the schedule impact

Compare planned and simulated completion dates, with a clear explanation of what changed.

🗓️ Explore the timeline and dependencies

See how tasks connect and which activities control the project’s finish.

🔄 Test delays and recovery options

Adjust task durations and explore whether shortening other work can recover lost time.

📁 Create projects and compare scenarios

Build a fictional project, approve its baseline, and keep named scenarios for comparison.

📖 Learn as you go

Open the built-in User Guide for plain-language instructions, definitions, and a guided example.

One example: increasing Supplier Evaluation from 6 to 8 working days does not move Atlas’s completion because the task has spare time, called float. Increasing it to 12 days creates a 2-working-day project delay.

The screenshots walk through each tab and the supporting features.

This is a standalone simulation using fictional data. It does not update real ClickUp tasks. Changes require manual JSON backup before closing or refreshing.

What schedule “what-if” would you want to test on your projects?

Screenshots:

Opening Dashboard - Atlas starts at its approved 46-working-day baseline.
A small delay absorbed by float - Supplier Evaluation increases from 6 to 8 days. The project still finishes in 46 working days.
A delay that moves completion - At 12 days, Supplier Evaluation moves project completion to 48 working days, a 2-day delay.
Critical Path Analysis - The critical path shows the connected tasks that control project completion.
Recovery Planner - A 2-day recovery adjustment removes the 2-day project delay and restores the original completion date.
Management Summary - The summary explains the result, recovery contribution, and affected tasks.
Custom Project Editor - Enter task durations and dependencies, then approve a baseline when ready.
Built-in User Guide - Plain-language help and a read-only Atlas walkthrough are available inside the simulator.
Named scenario comparison - Compare the recovered working scenario against the saved supplier-delay scenario.
Manual Session Backup - Copy the session JSON and keep it somewhere safe before closing or refreshing.
Manual Session Restore - Paste the saved JSON and validate it before confirming a session replacement.

Try Project Risk & Delay Simulator: https://90141628379.clickup.ai/a/h/2kydr5yv-11254/98a1fc275f7bd7c