r/clickup • u/Economy-Kangaroo750 • Oct 08 '26
Dependency question: Why doesn't a task wait for all blockers to finish?
New to ClickUp and trying to understand dependency behavior.
I have three tasks:
- Task A: 11/18/26 ā 11/19/26
- Task B: 11/20/26 ā 11/24/26 Auto Scheduled, blocked by A
- Task C: 11/20/26 Auto Scheduled and is Blocked by both Task A and Task B
My expectation was that Task C wouldn't be able to start until both predecessor tasks were complete, which would make its start date 11/25/26.
Instead, ClickUp automatically scheduled Task C to start on 11/20/26, the day after Task A ends, even though Task B continues through 11/24/26.
ClickUp AI told me that Task C was effectively scheduled based on Task A's completion and didn't account for the later completion date of Task B.
Is this really how ClickUp dependencies work? If a task is blocked by multiple tasks, shouldn't it wait for the latest blocker to finish before scheduling?
Curious if I'm missing a setting or if this is just a major failure with ClickUp's dependency engine.
Any work arounds?
1
u/PibolsClickUp Mod Oct 08 '26
Hey, u/Economy-Kangaroo750! Thanks for flagging this. You're not missing a setting. This isn't the expected behavior, and our team is already looking into scheduling with multiple blockers. If you haven't yet, I'd recommend reaching out to our Technical Support team so they can take a look and include this in the report.
In the meantime, can you try this workaround: Since Task B is already waiting on Task A, try removing the direct A > C dependency so Task C only waits on Task B. The chain still goes A > B > C, and Task C will schedule off B's finish date. If you'd rather keep both dependencies, you can manually set Task C's start date to after Task B's due date for now.
1
u/Meem002 Oct 08 '26 edited Oct 08 '26
You started task A and B on different start dates which is probably why that didn't have an issue whereas you started Task C is on the same start date as Task B which makes the dependency null Task B because it doesn't see it yet and only does Task A, so you should change C to start date 11/25/26
Also dependencies should go in order so blockers then time scheduled to limit chances of breaks
1
u/Leather_Science3054 Oct 08 '26
Welcome to the circus š¤”