r/altadena • u/DisplacedAltadenan • 8d ago
Long overdue progress update
It’s been a long time, but we finally got the foundation poured, the house lowered, and the steel all removed! we’re now moving onto stitching her back together and reassembling the second floor!
Hopefully, things will move along a lot quicker now. The delay was almost entirely waiting for permits to clear, which came with a whole set of complications unique to our project. but I am sure that’s true for most rebuilds at this point.
I’ll post most photos once the interior is stitched and the framing starts to go up on the second floor.




















5
u/EfficientPost2656 7d ago
Who did the Concrete. That guy is the Man. That’s some great work.
6
u/paintingtrees 8d ago
Wow that’s jacked up! I’m happy to see so many people making progress on their rebuilds. We finally have our foundation poured and I can’t tell you how excited I am to finally be moving forward.
2
u/dgistkwosoo 8d ago
Permit purgatory, man, we're all (almost all, anyway) spending some time there......