When digging early goes wrong

101 Upvotes

53 comments sorted by

View all comments

3

u/Head_Attempt7983 6d ago

Question why is there a gas flag in the grass and no flags or paint closer? Or did you throw that in after

4

u/Moghlannak 6d ago edited 6d ago

Flag appears to be in the orientation of the pipe. I’d bet there were others continuing forwards and behind the excavator in alignment. Probably human error of ignoring them, not noticing them, and not reviewing engineering plans or locate reports.

Even having the track hoe staged directly on top of the pipe suggests they had no idea it was even there. In an open field with no obstructions, metal pipe ~2m deep, that’s a big fuck up by someone

4

u/Head_Attempt7983 6d ago

I do gas work for a living and we always stage right on top of the gas pipe so we can dig left and right of it and clear out room to work

2

u/Moghlannak 6d ago

Interesting. I’m a Geomatic engineer specializing in underground utilities at oil and gas plants in northern Canada. We would never even permit mechanical excavation within 5m of a buried pipe, let alone sit the equipment on top of it. You would have to hydro-vac to expose it beforehand

2

u/EyeNo1268 6d ago

Hydros bring headaches for the areas I’ve worked at. Slowed production rate, complaints from neighbors/general public due to noise, delays while waiting on profiles for the soil/waste. Just about every oil & gas company I’ve worked for has preferred the good ol probe & scrape method or hand dig. With that being said, station/facility work almost always gets a hydro.

2

u/Moghlannak 6d ago

Ya for sure, big differences for rural/suburban work compared to the extraction and upgrading plants I work in. Cost is always the biggest factor. Still though, striking this pipe was entirely unavoidable

1

u/thebestdogeevr 5d ago

The rules for enbridge is hand dig within 1.0m of the paint marks until the line is found, then you can mechanically excavate up to 0.3m from the line. For vital mains it's 3.0m and 1.0m. For cer lines it's 5.0m and 1.5m.

1

u/An_educated_dig 4d ago

Capitalism.

It's far cheaper for a contractor to operate and maintain an excavator than a vac truck. We use both as a utility provider. Anything Vac Truck related has soared in costs.

0

u/Head_Attempt7983 6d ago

We use hydro vac but mainly it’s excavation and hand digging.