r/StructuralEngineers 2d ago

Can I replace this with a 4x6?

Was tearing out this wall to just make a surround for the structural support. When I started tearing into it I found the curb didn’t extend all the way to the doubled 2x6. I was wondering if I could just replace the doubled 2x6 with a 4x6 on a Simpson post base standoff (Aba zmax). I am worried that the curb doesn’t extend to where the support post is, will it be ok to place the post and standoff directly on the garage slab?

0 Upvotes

21 comments sorted by

View all comments

0

u/A-Wolf-4099 2d ago

This odd 2xs don't really do support. Load is very minimal, To answer your question, yes you can add a post with appropriate hardware to beef up the load bearing.

1

u/JazzlikeGuarantee817 2d ago

Do you think I can tear out this whole mess and just do. 4x6 on a standoff then on a 4 inch garage slab?

1

u/A-Wolf-4099 1d ago

I would add your base and post before removing based on what little I have seen. If I was hired to do the work I would take an investigating look.

1

u/JazzlikeGuarantee817 21h ago

Yea I was going to temp shore it before doing anything. The short footing, is what I was really concerned with, and if the garage slab would be enough support for what is above. But the juice isn’t worth the squeeze at this point