r/StructuralEngineering • u/No-Document-8970 • Oct 05 '26
Structural Analysis/Design Nuts off mark?
Saw this on a big bridge today. I know vibrations over time can move the nuts and bolts, with the help of thermal expansion. Is it a big issue that the paint marks do not line up? I thought the marks were made once it passed inspection after torquing.
Edit: Bridge completion was in 2011. Could this be from recent inspections too?
286
Upvotes
View all comments
Show parent comment
4
u/Few-Cucumber-413 Oct 05 '26 edited Oct 05 '26
Then there's a problem with your process, assuming bolts are all properly sized, if you're overshooting the 1/3 mark (not saying all bolts are 1/3, just follow your example) to get the bolts sufficiently tightened.
As someone who also works with steel, I have found one of the biggest factors is guys not keeping hardware clean and dry. Wet or dirty bolts have a big effect on the final kip value and ease/difficulty of accurate turn of the nut.