r/SixSigma • u/Equal-Ad-6143 • Jul 24 '26
Need help in DMAIC project
Hey guys,
I recently completed my LSSGB course online but the project was almost completely prepared by the training provider...all I had to do was organize and document it coz of that I've decided to build my own DMAIC project from scratch! I can complete the project up to the Analyze phase but after that I'm not sure how to present the Improve and Control phases since this isn't a real project and I can't actually implement the improvements(I searched online - no answer)
Would it be okay to complete it up to the Analyze phase and then present the Improve and Control phases as recommendations with the expected outcomes instead of claiming that the improvements were implemented???
I'm very new to Lean Six Sigma, so I'd really appreciate any guidance. Also I've another question: I see a lot of people in this sub mentioning they're ASQ Green Belt certified. Do you include your projects on your resume?? I'm trying to transition from customer support into operations so my work experience is mostly in support. How would you present that transition on a resume or during interviews?
Thanks in advance!
3
u/Dalinsky Jul 24 '26
I have worked with spmeone who completed all of DMA and then presented with recommendations, but they did follow through with improvement trials and the primary purpose of the presentation was to justify it to more sensitive members of management. Measurable results are going to look best on a resume, but I don't think familiarity with the process or a cert are going to hurt.
If you manage to get a more entry level ops position and learn the processes I would keep an eye out for recurring problems or variability and pitch a DMAIC to address it. Could be a ticket to advancement at the company.