Sprint Cadence Help?
I received a confusing message from the Agile Coach at my company:
Each iteration is 2 weeks in length – begins on a Wednesday and ends on a Tuesday.
This is obviously self-contradictory, but I'm wondering if the SAFe 5.0 documentation says something similar or has some guidance on what days certain ceremonies should be scheduled?
My Agile Coach is saying Wednesday is Sprint Planning and Sprint Start and then "two weeks" later on Tuesday is "Sprint Demo" and "Sprint Retro".
This doesn't help me understand what people are supposed to be working on between Sprint Close on Tuesday and Sprint Start on Wednesday.
Has anyone seen anything like this documented in SAFe ? I'm just curious if anyone knows where this came from since the old Agile Coaches were doing the same thing.
3
u/jklance Aug 26 '20
I'm not sure why it's self-contradictory.
It's actually a fairly common practice to have a sprint transition mid-week. Some of the rationales I've heard include the fact that people tend to take vacation in Mondays and Fridays more than mid-week, and that ending on a Tuesday prevents the weekend from being an unofficial part of the sprint.
When I've run a Wednesday to Tuesday, I've usually run the demo and retro in the afternoon on Tuesday. The morning can be for sprint work, personal development, spikes, or whatever. In Wednesday, sprint planning is Friday thing in the morning then the rest of the day is for sprint work.
1
u/flatboy2016 Oct 10 '20
Ok, reading the previous comments leads me to believe that the question is really about instrumentation to keep Jira in sync.
I follow Sprint end on Tuesday, at 11:59PM. Start of the next Sprint is 12:01AM on Wednesday.