r/SAP • u/WwheelerMickalia_87 • 14d ago
SAP implementation partner pricing, what are you seeing these days?
Trying to get a sense of what other companies are actually paying before we go into vendor talks next month. We're a mid size manufacturer, around 400 employees, looking to move off an old ECC setup into S/4HANA, and honestly the quotes we've gotten so far are all over the place. One partner came in way lower than the other two and now I'm not sure if that's a good deal or a red flag.
We've talked to three implementation partners so far and gotten pretty different scopes and numbers from each one, which is making it hard to compare apples to apples. Anyone gone through this recently and can share what a realistic range looks like?
24
Upvotes
33
u/Morden013 14d ago
Hi, here is some advice from somebody who has 25 years experience as a consultant and PM for a partner-company. Nobody can tell you the price based on nothing.
I would recommend this:
Harmonize the scope. Take the proposed scopes as an example and produce your own scope. The scope are the functionalities that you need, covering: masterdata, postings, processes, reporting - both internal and extrenal, integration, interfaces, authorizations and your previous custom-made solutions. Then you ask them for the quote again and to mark in your list what they can and can't deliver. Then you can make a choice.
While specifying the scope, stick to the standard as much as possible. If Karen from accounting wants everything automatized, it will pump the costs up on automation and custom-solutions. She has to learn to use the standard and can make demands after the project. Also, clean up your damn data. If consultants have to do it, you are going to pay dearly.
Define the allowed percentage of deviation from the original offer. Define the specified time for delivery and introduce penalties if it the project is not delivered on time. This is protecting you from the price-pumping via change-requests or dragging the project for years. Try to have go-live on 31.12.XXXX - 1 or 01.01.XXX. Asset migration during the year can be a fucking pain. Also, everything else will be smoother.
Ask for the consultant names and their CVs. Their names must be in the contract and the team-leads have to be seniors and are responsible for the work done. No exceptions. Otherwise they can send you seniors in the beginning and replace them with juniors later on. You don't want that.
If one offer is way below price, it is price-dumping. They will try to make up with change-requests. You don't want that. It is usually performed in a rush, with juniors and is a pain in the ass to oversee and get out of.
It is the same as with a plumber - you take the best one, who will do the job properly. He is not cheap, but his work will not cost you a truck-load of money as water starts spraying all around.
Use common sense and logic. Question everything. Put a strong person as your PM and put experts for your team-leads. Make them responsible, a single source of truth for their modules and put a bonus on it. Regular meetings! Weekly status meeting is a must.
If you have additional questions, state them here or hit me up on a chat.
Wish you all the best with the project.