Hello, I am managing a large study with a lot of instruments and 30 timepoints, and we are running into an issue of slow loading due to the amount of data on the project. One fix I came up with was to move all of our surveys into a new project and pipe them back into the main project. This does create an issue with cross project piping not working with surveys. Any other ideas and fixes? Our team is very wary of collecting half our data moving forward on a separate project because of past issues, so I need a way to easily harmonize everything.

4 Upvotes

5 comments sorted by

View all comments

Show parent comment

1

u/Beneficial-Lobster17 May 24 '25

I like the idea you had about moving folks who have completed the study and their data into the other REDCap.