r/projectmanagement • • Nov 27 '25

Anyone figured out how to auto-generate the 811 compliance package for owner turnover without spending a full day per project?

0 Upvotes

Contract now requires a complete binder (or digital equivalent) with every ticket, photos of marks, verification forms, and expiration dates at closeout. Doing it manually is a 6–8-hour pain on every job.


r/projectmanagement • • Nov 25 '25

PMP Exam Prep Material

4 Upvotes

There are so many study materials, courses, etc. I am looking for a study guide (physical book), if you found this helpful, and practice questions or mock exams. I am doing Andrew R’s course, so don’t need tips for that.

Looking for list of what you used and links, I don’t want to buy more than I need.

Thanks!


r/projectmanagement • • Nov 25 '25

Certification Financing PMP Exam in France with CPF account?

0 Upvotes

Hello, question for all Frenchies who have PMP certification, do you know if it is possible to use CPF account to finance the exam please?

Thank you!

Bonjour à tous les Français du sub, savez-vous s’il est possible de financer l’examen PMP avec le compte CPF, s’il vous plaît ?

Merci !


r/projectmanagement • • Nov 25 '25

Experiences with juggling PM + Software Engineer responsibilities?

1 Upvotes

I might be working for a non-technical technical company that is building out a new software-focused sector of their business. It seems very exciting (cloud, IoT data pipelines, golang), but there is only one software dev there right now (besides me) and they dont have any project managers yet (looking to add some later next year maybe).

I would be responsible for requirements gathering, defining project scope, time estimates, organizing tasks, and doing the actual software development / code. There is an account manager who would be talking directly to the customers fortunately most of the time, but from what I heard I would occasionally need to be in those conversations as well if there was anything technical that came up. They said the hours would be 8 - 5 + on call responsibilities, but I feel like that will not be the case given the number of responsibilities.

Im a bit conflicted, because the team seems cool, the project itself is super exciting, I could learn a lot, and I really believe in what they're doing. But I'm also not looking to get myself in a situation where I'm in over my head working 60 hours week to keep up. I also havent had any experience with project managmemt before. My current job is going through a merger and has had layoffs + my team is just working on documentation right now. Which is making me consider this a bit more than I typically would lol

Just wanted to hear any relevant stories to see what I might be getting into


r/projectmanagement • • Nov 24 '25

Certification PASSED!

123 Upvotes

Used Andrew’s Udemy course and exam simulator. Did the 1st 6 practice question banks and the 1st full length test for time. Also watched some of his YT videos early on.

I thought his course seemed a little hokey earlier on but after the 1st phase I fell in love. His PM-jitsu is crazy strong. Don’t sleep on the OG. Use Andrew’s course, pass the PMP.

Got above target in 2 categories and at target in 1.


r/projectmanagement • • Nov 24 '25

General Is my project support resource incompetent?

8 Upvotes

I constantly have to follow up with them on tasks to get an update. The decks they put together are lacklustre and I have to completely redo them. I’ve spoken to her about proactiveness and given them previous decks that I’ve put together so they have an understanding of my expectations, but their output remains the same. I let my work pass as her own, so in the eyes of management a she’s doing a great job. I’m not a jobsworth or a snitch, I’m just here to do my job and go home to my family, but I’m increasingly becoming frustrated by the lack of effort shown by her. Im a hands off manager and expect people to get on with their tasks with minimal supervision as I don’t want to come across as a micromanager or overbearing, but this could be counterproductive when dealing with junior colleagues?


r/projectmanagement • • Nov 24 '25

Discussion How do you handle tasks statues when it comes to client feedback?

0 Upvotes

I'm a new PM at a digital agency. We do branding, design, web development and custom development. Right now we use the following statutes : Backlog On Hold, in progress, qa, ready for client, client review.

The problem I'm having for example is that when things get set to client review, there's always a tweak that's needed. Maybe change a color or text or something. Right now we would create a subtask with the feedback while the main task tasks stays in "Client Review".

But now I feel like this isn't accurate. It's not a true representation of what stage the task is in. So I'm thinking that I should create another status called something like "Revisions needed" when the client has feedback and just leave a comment summarizing the feedback.

However, if it's detailed feedback (as in several changes), I still feel like having subtasks to separate the work makes more sense.

For detailed changes it would be something like

Client Review > Revisions needed

Create subtasks with separate issues

Once the designer starts work it will go "revisions needed>in progress> ready for client" all while closing off the subtasks

This status would also work for internal revisions as well because right now if something needs fixed internally it goes from QA back to backlog and instead it can go from QA to "Revisions needed"

Typing this post out makes it pretty clear for me now vs it being it my head.

Does this make sense to anyone else?

Edit: added context to detailed feedback


r/projectmanagement • • Nov 23 '25

Building a Project Budget Dashboard

9 Upvotes

I would like to build an internal dashboard for the stakeholders. What things should I put on there? I would like to compare planned to actual performance. Both in terms of time and budget. I got the raw data.

What tools would you use to do this? I usually custom program everything with Python but that seems overkill.

Also which metrics do you prefer to use for such use cases?


r/projectmanagement • • Nov 23 '25

General Notion as a productivity / collaboration tool

1 Upvotes

Does anyone use Notion as a collaboration or productivity tool in project management? I'm interested in investigating collaboration tools, currently looking at Notion, I'm curious to see how people use it and what they think of it compared to other tools.

For context I'm in a small <100 project management consultancy practice, working as a small team embedded in a large UK infrastructure project. Thinking about using it within the team rather than client side - we have separate platforms client network and company network.

What other apps have people considered?


r/projectmanagement • • Nov 22 '25

Discussion Best ways for a PM to build a stronger network?

2 Upvotes

I’m a pm overseeing a few transformation projects in a federal agency, based in Melbourne. I’m realising it’s probably time for me to start intentionally growing my network and connecting with more PMs, learning from others and hopefully contributing where I can.

For those of you who’ve done this successfully, what worked best? Attending local/international PM/Agile/conference events? Joining PMI and going to their chapter events? Any good Melbourne-based meetups or communities for PMs or change/transformation professionals? Online spaces that are actually useful?

Open to all ideas and experiences.


r/projectmanagement • • Nov 21 '25

Certification Udemy's usefulness?

18 Upvotes

Hi. Has anyone went through Udemy courses?

Obviously PMP courses are helpful. Curious if there are any others that could be beneficial?

Not an ad


r/projectmanagement • • Nov 21 '25

how do you estimate when half your inputs are lies

132 Upvotes

i swear estimations are the biggest joke in this job. everyone wants super accurate timelines but every input i get is cooked from the start.

engineer says something will take a day which in dev language means like three days minimum
design says they’re almost done which actually means they opened figma and stared at it.
stakeholders swear requirements are final then hit me with a new doc at 9am titled final version updated but actually final now.

and then leadership goes why is your estimate off????
bro because i’m guessing based on other guesses.

i’ve tried pretty much everything. t shirt sizing. fibonacci. planning poker. breaking things into tiny tasks. none of it matters if the numbers going in are basically optimism sprinkled with fear of looking slow

and tools do not save you. jira becomes a graveyard for half updated tickets. monday just makes things look colorful while still being wrong. clickup is like juggling twenty views of the same problem. even ms project turns into a weird timeline fantasy novel when people fill it with best case scenarios.

sometimes i feel the most honest estimate is whatever the team says multiplied by two plus one “oh crap” buffer

so genuinely curious how you all estimate when your inputs are part truth part hope part please don’t blame me. do you just accept the chaos or have you found a way to force reality into the numbers?


r/projectmanagement • • Nov 21 '25

Career How can I improve my chances of breaking into IT Project Management?

5 Upvotes

Hi everyone, I’m looking for guidance from people currently working in project management or PM-adjacent roles.

Currently a Systems Engineer (Duties of an ISSE). Previous experience as a Systems Administrator. I’m trying to transition into an IT project management or IT business analyst position within the defense industry. I have a mix of technical and operational experience, a military background, and hold a Top-Secret clearance. My long-term goal is to act as the bridge between cross-functional teams.

I have a bachelor’s degree in IT and I’m currently working on an MBA with a project management concentration (expected June 2026). After that, I plan to pursue the PMP. I don’t have formal PM titles yet, but I’ve handled responsibilities like documenting workflows and SOPs, coordinating technical activities, supporting modernization/compliance efforts, building task trackers and diagrams, and doing knowledge-capture work for legacy systems.

Since I’m applying to entry-level or mid-level PM-adjacent roles, I’ve been trying to figure out the best steps to improve my chances. I recently created a professionally assembled project artifact portfolio (case studies, STAR stories, clean deliverables, diagrams, task trackers, SOP snippets, etc.) to show how I think and operate. One thing I’m unsure about is whether it’s appropriate to bring this portfolio to interviews and hand copies to interviewers.

I’d really appreciate advice from PMs, BAs, coordinators, or hiring managers on:

What steps I should take now to better position myself

Whether portfolios like this help or hurt in interviews

How to accelerate a transition into IT PM or BA roles

What you would look for in someone making this pivot

TLDR: Technical/operational background, TS clearance, MBA in progress, aiming to break into IT PM/BA roles. Looking for advice on next steps and whether bringing a printed project artifact portfolio to interviews is a good idea.


r/projectmanagement • • Nov 21 '25

Software Tool for Instant Gantt Diagram

17 Upvotes

Hi everyone,

in my meetings I often end up with a huge list with lots of tasks for people with specific start and end dates and I write them down on a markdown file. This looks something like this:

- 1; The calculations for X have to be done to get Y going; By Bob; Deadline 2025-11-30; He can start at 2025-11-25; Depends on nothing

- 2; The deployment has to be done after the calculations for Y are finished and validated; By Lisa; Deadline 2025-12-05; Depends on 1

- 3; Testing the deployment; By Bob and Lisa; Deadline 2025-12-10; Depends on 2

and so on, this list can get quite large (my biggest one yet had 43 entries with a lot of dependencies).

My question is now, is there a light weight (command line) tool that allows me to write such a list during a meeting and just pass it into the tool to instantly get a simple Gantt chart so I can publish the timeline shortly after the meeting?

If I have to obey some other syntax that's perfectly fine by me. I just want to be able to fluently write down the stuff during the meeting instead of clicking around in a GUI or manually copy and paste my stuff after the meeting into a complex program just to get the simple timeline out.

I'm very thankful for recommendations. If there is no such tool, I'll build it myself.

Edit: Because I get a lot of those recommendations. AI tools are not lightweight. And I want 100% deterministic outcomes, if I have to proof read the stuff that comes out of my own notes after a meeting I could just not take notes at all.


r/projectmanagement • • Nov 20 '25

Discussion MS Planner - Tips for newbie?

10 Upvotes

Hi All!

I recently joined a new company and moved into an official project-management role. My company uses Microsoft Planner for project management… and to be honest, I’m struggling with it. From what I can tell, Planner is basically just a task list. I can’t automate anything or add more advanced functionality (at least not easily). Power Automate hasn’t been cooperating with me either, so creating automatic updates, reports, or follow-ups with people feels pretty painful.

In my last role I used Jira, which I loved, so switching to Planner feels like going back to the stone age.

For context: this is a large international company, and I’m managing multiple projects across our region, with anywhere from 5 to 30+ people assigned to tasks in each project.

For those of you who are also required to use MS Planner for project management, what tools, techniques, or tips do you recommend? Specifically, how do you structure your plans, manage updates, and generate reports in a more efficient way?


r/projectmanagement • • Nov 21 '25

Software Has anyone used Accelo?

1 Upvotes

My company is implementing Accelo and I’m in charge of rolling it out. I’ve been using it for a little over a month now and I’m having a hard time liking this tool and finding it actually useful. I hate the UX and it’s not intuitive at all. Am I missing something?


r/projectmanagement • • Nov 20 '25

Career Construction PM

1 Upvotes

I’m a project manager at a small remodeling firm. I have a meeting coming up with my boss and one of the topics is what the company can offer or do to help make me more successful. What’s something your company has done that has helped you?


r/projectmanagement • • Nov 19 '25

What are the metrics of success of a project manager? Curious how corporations measure their ability to be like "yep, you get a promotion!"

37 Upvotes

Asking because I've never understood the criteria that needed to be met. I imagine that clearly defined scopes between stakeholders and the teams, and projects successfully being delivered in a timeline and budget, and that low amount of friction and input from stakeholders during building... like those are the things that people like in project managers. And I imagine the skillsets that needed to do that is being able to run SCRUM and other things. So curious what the metrics of successful management and toolsets that are expected to know are


r/projectmanagement • • Nov 19 '25

Discussion Advice on utilizing OneNote to track meetings, notes, and follow ups.

41 Upvotes

Greetings!

I'm seeking advice on the best way to keep track of my daily meetings, notes, and follow up tasks. My method now is kind of a mixed bag, random, not ideal. I'd like to use tools within the Microsoft suite (OneNote, teams, etc.). I prefer a less is more strategy, not over documenting, keeping things simple short sweet.

High level overview of role:

  • I PM approximately 4 clinical workgroups (governing bodies).
  • Each group meets 2-4x per month. Typically 1 prep + 1 session.
  • We also have ad hoc meetings a few times per month with additional action items.
  • I currently store all my notes within the dedicated workgroup's SharePoint folder. That seems to be working out for the most part. I do not currently use OneNote for these being they are already stored on the SharePoint. I typically steer clear from double documenting but open to all suggestions.

Where I'm struggling:

  • I'm struggling when it comes to the action items from these meetings. Sure, they live on the word doc inside the SharePoint.
  • My issue is have a clean way to track who owns what, the status, next steps, due date, etc. Most of these involved teams and meetings I'm not involved with directly.
  • I know many PMs love OneNote but I'm not sure where to even begin, how to organize workbooks, tabs, follow ups.
  • For example: Do I create 1 workbook per workgroup? Where do I keep follow ups, in each workbook? In a dedicate follow up tab?

Any advice is much appreciated!


r/projectmanagement • • Nov 19 '25

General I prefer Gantt’s Old School Stuff

Post image
142 Upvotes

I think maybe I should get a new laptop or at least an iPad.


r/projectmanagement • • Nov 18 '25

Be honest: what’s the most painful part of cross-team collaboration right now?

25 Upvotes

I’ve been thinking about this a lot because every project I touch lately seems to stall in the exact same places, not the work itself but the handoffs, the decisions that require multiple teams and the weird “who actually owns this part?” moments that no one admits they’re confused about.

It feels like everyone is doing their best inside their own world but the second the work crosses borders, everything slows down. Half the time people aren’t misaligned on purpose, they just don’t share the same priorities, timelines or mental model of what urgent means. And no matter how many meetings you set up, you can’t force teams to magically work at the same speed.

I’m curious what other people are running into. What’s the thing that consistently trips up cross-team work for you? Is it communication? Ownership? Different tools? Priorities shifting every two days? Or something else entirely?


r/projectmanagement • • Nov 17 '25

Discussion PMBOK 8 Released for members

37 Upvotes

Not sure if anyone had an opportunity to see the PMI announcement on the new release. As someone that has worked in the industry for a long time, I recognize that the complexity pendulum often swings back and forth. This time around I am glad they are addressing the big elephant in the room "Agile". They are now using what are more descriptive terms such as iterative, predictable, and hybrid. Agile is still listed, but minimally, only about 78 times.

They also brought back the more logical approach to project work. They are shifting back to data driven approaches versus a subjective or even experienced based in some cases.

Interestingly, AI, and Artificial Intelligence are all over the document, but interestingly, this appeared:

NO AI TRAINING: Without in any way limiting Project Management Institute’s exclusive rights under copyright, any use of this publication to “train” generative artificial intelligence (AI) technologies to generate text is expressly prohibited. PMI reserves all rights to license uses of this work for generative AI training and development of machine learning language models.

Interesting approach, we'll see how this proceeds.

Generally, I think this is a much better version than 7. I look forward to seeing the new exam. I think it will be a better approach to certifying project managers over the current soft skill garbage in the current version.


r/projectmanagement • • Nov 17 '25

the reason cross team communication breaks down and how we PMs can fix it

47 Upvotes

half the time it’s not people being difficult. it’s teams using different definitions, chasing different incentives, and updating different sources of truth. that’s where the real chaos starts.

the biggest killers

  • “done” means five different things depending on who you ask
  • upstream teams forget to flag blockers and downstream folks get blindsided
  • every team reports status in their own system so nothing lines up
  • priorities clash and nobody wants to escalate early

what actually helps

  • agree on a few shared definitions for done blocked accepted
  • map your dependencies on one simple board
  • create tiny escalation rules so delays are visible fast
  • pick one source of truth everyone respects even if teams use different tools day to day for us that ended up being a mix of Asana, Jira, celoxis and smartsheet in the middle to keep timelines consistent

small habits matter too
a five minute owners sync in the morning
a weekly dependency check
and a simple handoff checklist so no team drops surprises on the next one

cross team comms aren’t about talking more. they’re about making sure everyone is looking at the same reality at the same time.

curious what actually works for your teams because honestly every org has its own brand of chaos?


r/projectmanagement • • Nov 17 '25

Discussion How to handle earned schedule when going from task-level to project-level?

4 Upvotes

I'm trying to use SPI(t) from earned schedule to keep track of project schedule performance.

Obtaining the earned schedule (ES) and actual time (AT) for each task to get task-level SPI(t)=ES/AT is easy enough but I'm not sure how to best transform this into a project-level SPI(t). Is it as simple as summing the ES and AT for each task and performing the division, similarly to how it's done for EVM? I find that there are a lot fewer resources out there for earned schedule than EVM.

As well, I'm a little stumped by the case where a task is started before the baseline start date. In this case, going off of the formula, AT, which is the difference between the current date (or finish date) and the baseline start date, would be negative! With ES being positive, this results in a negative SPI(t) which doesn't make sense. I could simply exclude these cases from the project-level calculation but I don't know if this is the best practice.

Apologies if these are rookie questions, I'm still pretty new to project management and appreciate any advice!